United States › Grid › Interconnection queues › California

BATTERY STORAGE · CAISO

Adrian Storage

Adrian Storage is a 55.5 MW battery storage request withdrawn in the CAISO interconnection queue, in San Mateo County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedJul 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1905
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Millbrae 60 kV
Location
San Mateo County, California
Technology
Battery: 55.5 MW
Total requested
55.5 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2021
Proposed online date
October 2031
Withdrawn
July 2024

Location

Marker shows the centre of San Mateo County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Mateo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem