BATTERY STORAGE · NYISOAllegany 2 Battery 2
Allegany 2 Battery 2 is a 20.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Allegany County, New York, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2021 (completed)
- Withdrawn / abandonedJan 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1128
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- Northland Power U.S. Projects
- Connection point (POI)
- Andover-Palmeter 115 kV Line 101990
- Location
- Allegany County, New York
- Technology
- Battery: 20.0 MW
- Total requested
- 20.0 MW
- Queue status
- Withdrawn
- Entered queue
- 21 January 2021
- Withdrawn
- January 2023
Location
Marker shows the centre of Allegany County; the queue data does not give exact sites.
Other requests in Allegany County
- Zenobe Burns LLCBattery storage · 100 MW · in study
- Moraine Solar Energy CenterSolar · 93.5 MW · in study
- Nine Mile Wind EnergyOnshore wind · 200 MW · withdrawn
- Nine Mile Wind FarmOnshore wind · 120 MW · withdrawn
- Sapphire SunSolar · 120 MW · withdrawn
- Cold Creek SolarSolar + storage · 120 MW · withdrawn
- Allegany WindOnshore wind · 100 MW · withdrawn
- Alfred Oaks SolarSolar + storage · 100 MW · withdrawn
- Zenobe Wellsville LLCBattery storage · 100 MW · withdrawn
- Moraine Solar Energy CenterSolar · 93.6 MW · withdrawn
- Cuba Wind ProjectOnshore wind · 86.5 MW · withdrawn
- Scio Solar FacilitySolar + storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem