United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 353

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 353 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J1954, Walworth County
Battery storage
35.0 MWWithdrawn / abandoned Walworth, WIMISO Aug 2021target 2025
Solar project GI-2014-2, Alamosa County
Solar
35.0 MWWithdrawn / abandoned Alamosa, COWest Mar 2014target 2016
Harrison Power Plant
Gas
35.0 MWWithdrawn / abandoned Harrison, OHPJM Oct 2017target 2024
Longbow Storage
Other · Cypress Creek Renewables
35.0 MWWithdrawn / abandoned Brazoria, TXERCOT Aug 2017target 2020
Solar + storage project AG1-550, Fluvanna County
Solar + storage
35.0 MWWithdrawn / abandoned Fluvanna, VAPJM Sep 2020target 2023
Solar project AG1-208, Montgomery County
Solar
35.0 MWWithdrawn / abandoned Montgomery, KYPJM Sep 2020target 2022
Onshore wind project H047, Steele County
Onshore wind
35.0 MWWithdrawn / abandoned Steele, MNMISO Jun 2008target 2011
Solar project IC-536, Montgomery County
Solar
35.0 MWWithdrawn / abandoned Montgomery, ALSoutheast Nov 2016
Solar project 57, Kittitas County
Solar
35.0 MWWithdrawn / abandoned Kittitas, WAWest Jan 2018target 2020
Battery storage project J1250, Clay County
Battery storage
35.0 MWWithdrawn / abandoned Clay, ARMISO Apr 2019target 2022
Solar project Q217, Yuma County
Solar
35.0 MWWithdrawn / abandoned Yuma, AZWest Sep 2017target 2014
Solar + storage project J2777, Madison County
Solar + storage
35.0 MWWithdrawn / abandoned Madison, INMISO Sep 2022target 2025
Gas project 214, Limestone County
Gas
35.0 MWWithdrawn / abandoned Limestone, ALSoutheast Sep 2008
Solar project AJ1-010, Mason County
Solar
35.0 MWWithdrawn / abandoned Mason, WVPJM May 2023target 2025
Battery storage project GEN-2018-051, Muskogee County
Battery storage
35.0 MWWithdrawn / abandoned Muskogee, OKSPP May 20182025
Nuclear project K27, Calvert County
Nuclear
35.0 MWWithdrawn / abandoned Calvert, MDPJM Jul 2003target 2004
Gas Turbine Capacity Increase ( See queue position
Gas
35.0 MWWithdrawn / abandoned Fairfield, CTISO-NE Dec 2007target 2010
Brookview Solar I
Solar
35.0 MWWithdrawn / abandoned Adams, PAPJM Aug 2016target 2023
Gas project AC1-184, Delaware County
Gas
35.0 MWWithdrawn / abandoned Delaware, PAPJM Oct 2016target 2019
Solar project 1037, Iron County
Solar
35.0 MWWithdrawn / abandoned Iron, UTWest Jun 2018target 2021
Solar project 254, Putnam County
Solar · Third Party
35.0 MWWithdrawn / abandoned Putnam, FLSoutheast Jun 2017target 2026
Solar + storage project J2820, Daviess County
Solar + storage
35.0 MWWithdrawn / abandoned Daviess, KYMISO Sep 2022target 2025
Solar project AE2-091, Cumberland County
Solar
35.0 MWWithdrawn / abandoned Cumberland, NJPJM Jan 2019target 2022
Other project J234, Midland County
Other
35.0 MWWithdrawn / abandoned Midland, MIMISO Nov 2011
Solar + storage project C1-31, Klamath County
Solar + storage
35.0 MWWithdrawn / abandoned Klamath, ORWest May 2021target 2025
Solar project AH1-164, Franklin County
Solar · Robin Ridge Solar, LLC
35.0 MWWithdrawn / abandoned Franklin, VAPJM Mar 2025target 2024
Permian Wind
Onshore wind · Permian Wind, LLC
35.0 MWWithdrawn / abandoned ERCOT Oct 2005
Solar project GEN-2016-166, Washington County
Solar
35.0 MWWithdrawn / abandoned Washington, ARSPP Nov 2016target 2019
Other project G0444, Cowlitz County
Other
35.0 MWWithdrawn / abandoned Cowlitz, WAWest Sep 2010target 2011
Solar
Solar
35.0 MWWithdrawn / abandoned Merrimack, NHISO-NE Nov 2019target 2022
Gas project I02, Ashtabula County
Gas
35.0 MWWithdrawn / abandoned Ashtabula, OHPJM Feb 2002target 2007
Solar + storage project J2324, Winnebago County
Solar + storage
35.0 MWWithdrawn / abandoned Winnebago, ILMISO Sep 2022target 2027
Solar + storage project AF1-305, Mercer County
Solar + storage
35.0 MWWithdrawn / abandoned Mercer, PAPJM Sep 2019target 2023
Solar project 963118, Anderson County
Solar
35.0 MWWithdrawn / abandoned Anderson, SCSoutheast Sep 2024
Solar + storage project J2781, Jasper County
Solar + storage
35.0 MWWithdrawn / abandoned Jasper, INMISO Sep 2022target 2025
Solar project AG1-327, Franklin County
Solar
35.0 MWWithdrawn / abandoned Franklin, PAPJM Sep 2020target 2023
Solar + storage project AG2-317, Barren County
Solar + storage
35.0 MWWithdrawn / abandoned Barren, KYPJM Mar 2021target 2024
Otay Mesa Energy Center Agp
Gas
35.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2014target 2016
Solar project IC-335, Dodge County
Solar
35.0 MWWithdrawn / abandoned Dodge, GASoutheast Feb 2014
Solar project Company EU, Lincoln County
Solar
35.0 MWWithdrawn / abandoned Lincoln, NVWest Apr 2010target 2022
Wind Project
Onshore wind
34.9 MWWithdrawn / abandoned Penobscot, MEISO-NE Jul 2007target 2012
Jerry Smith Energy Storage
Battery storage · Nexamp Solar LLC
34.9 MWWithdrawn / abandoned Tompkins, NYNYISO Sep 2024
Battery storage project AF1-047, Defiance County
Battery storage
34.8 MWWithdrawn / abandoned Defiance, OHPJM Jun 2019target 2023
Repowering Increase
Gas
34.8 MWWithdrawn / abandoned Norfolk, MAISO-NE Apr 2017target 2021
Solar + storage project AH2-407, New Castle County
Solar + storage
34.5 MWWithdrawn / abandoned New Castle, DEPJM Mar 2022target 2027
Onshore wind project GEN-2007-057, Moore County
Onshore wind
34.5 MWWithdrawn / abandoned Moore, TXSPP Dec 2007target 2009
Battery storage project AH2-406, New Castle County
Battery storage
34.5 MWWithdrawn / abandoned New Castle, DEPJM Mar 2022target 2027
Wood River - NG WRI DG Area Study #2 >5 MW
Solar
34.4 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2020target 2025
Solar project GEN-2008-102, Chaves County
Solar
34.2 MWWithdrawn / abandoned Chaves, NMSPP Aug 2008target 2010
Solar project GEN-2008-101, Lea County
Solar
34.2 MWWithdrawn / abandoned Lea, NMSPP Aug 2008target 2010
Page 353 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)