United States βΊ Grid βΊ Interconnection queues βΊ Indiana
SOLAR + STORAGE Β· MISOSolar + storage project J2777, Madison County
Solar + storage project J2777, Madison County is a 35.0 MW solar + storage request withdrawn in the MISO interconnection queue, in Madison County, Indiana, connecting to DUKE ENERGY INDIANA.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedMar 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2777
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DUKE ENERGY INDIANA
- Connection point (POI)
- Cadiz Lapel Brockway Glass 69kV
- Location
- Madison County, Indiana
- Technology
- Solar: 35.0 MW Β· Battery
- Total requested
- 35.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 7 September 2022
- Proposed online date
- January 2025
- Withdrawn
- March 2023
Location
Marker shows the centre of Madison County; the queue data does not give exact sites.
Other requests in Madison County
- Battery storage project J1357, Madison CountyBattery storage Β· 150 MW Β· agreement signed
- Fall Creek Energy StorageBattery storage Β· 80.0 MW Β· agreement signed
- Solar project AI2-152, Madison CountySolar Β· 28.8 MW Β· in study
- Madison County SolarSolar Β· 100 MW Β· suspended
- Wildcat Wind Farm IOnshore wind Β· 200 MW Β· built
- Onshore wind project U4-039, Madison CountyOnshore wind Β· 710 MW Β· withdrawn
- Liberty II StorageBattery storage Β· 300 MW Β· withdrawn
- Gas project J3831, Madison CountyGas Β· 240 MW Β· withdrawn
- Solar project AH1-400, Madison CountySolar Β· 150 MW Β· withdrawn
- Lone Oak SolarSolar Β· 120 MW Β· withdrawn
- Solar project AD1-139, Madison CountySolar Β· 100 MW Β· withdrawn
- Battery storage project J1731, Madison CountyBattery storage Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem