United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· SPP

Onshore wind project GEN-2007-057, Moore County

Onshore wind project GEN-2007-057, Moore County is a 34.5 MW onshore wind request withdrawn in the SPP interconnection queue, in Moore County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2007 (completed)
  2. Withdrawn / abandonedAug 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2007-057
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Moore County East 115kV
Location
Moore County, Texas
Technology
Wind: 34.5 MW
Total requested
34.5 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
13 December 2007
Proposed online date
May 2009
Withdrawn
August 2013

Location

Marker shows the centre of Moore County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Moore County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem