Completed queue projects in the USA — page 34

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4,787563.7 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4,787 requests · page 34 of 96
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 220, Converse County
Onshore wind · Three Buttes Windpower
99.0 MWOperating Converse, WYWest May 2008target 2009
Coral Storage
Other · Copperhead Solar, LLC
99.0 MWOperating Falls, TXERCOT Feb 20212023
Haxelton Units 2-4
Gas
99.0 MWOperating Luzerne, PAPJM Apr 20002002
Onshore wind project G551, Howard County
Onshore wind
99.0 MWOperating Howard, IAMISO Sep 20052006
Onshore wind project 117, Carbon County
Onshore wind · PacifiCorp Commercial & Trading
99.0 MWOperating Carbon, WYWest Jan 2007target 2008
Onshore wind project GI-1001, Campbell County
Onshore wind · Campbell Cty Wind
99.0 MWOperating Campbell, SDWest Jan 2010target 2015
Solar project 631, Beaver County
Solar · Milford Solar I, LLC
99.0 MWOperating Beaver, UTWest Nov 2014target 2020
Solar project J808, Randolph County
Solar
99.0 MWOperating Randolph, ILMISO Jun 20172020
Onshore wind project 16, Walla Walla County
Onshore wind · Vansycle III, LLC
98.9 MWOperating Walla Walla, WAWest Nov 2001target 2009
Anchor Wind
Onshore wind · Ranchland Wind Project,LLC
98.9 MWOperating Eastland, TXERCOT Aug 20192024
Onshore wind project GEN-2008-079, Gray County
Onshore wind
98.9 MWOperating Gray, KSSPP Jul 20082011
Onshore wind project GEN-2012-033, Garfield County
Onshore wind
98.8 MWOperating Garfield, OKSPP Sep 20122015
Onshore wind project J503, Emmons County
Onshore wind
98.8 MWOperating Emmons, NDMISO Nov 20152019
Tavener 2
Solar
98.0 MWOperating Fort Bend, TXERCOT Dec 20162023
Onshore wind project J432, Brookings County
Onshore wind
98.0 MWOperating Brookings, SDMISO Dec 20142019
South Trent Wind Farm
Onshore wind · AEP Wind Energy
98.0 MWOperating ERCOT Feb 2006target 2008
Onshore wind project J652, Lafayette County
Onshore wind
98.0 MWOperating Lafayette, WIMISO Jul 20162017
Dresden
Gas
98.0 MWOperating Muskingum, OHPJM Oct 20162017
Onshore wind project G507b, Fond Du Lac County
Onshore wind
98.0 MWOperating Fond Du Lac, WIMISO Mar 20062008
Onshore wind project J395, Lafayette County
Onshore wind
98.0 MWOperating Lafayette, WIMISO Sep 20142015
Spring Grove I Solar
Solar
97.9 MWOperating Surry, VAPJM Oct 20162020
Laurel Mountain WF
Onshore wind
97.6 MWOperating Barbour, WVPJM Jan 20062008
Gas project Z2-112, Washington County
Gas
97.0 MWOperating Washington, OHPJM Apr 20142015
Timber Road II WF
Onshore wind
97.0 MWOperating Paulding, OHPJM Dec 20062011
Sunbury Generation Facility
Gas
97.0 MWOperating Snyder, PAPJM Apr 20152018
Gas project Q98, Pinal County
Gas
96.4 MWOperating Pinal, AZWest Sep 2022target 2024
Gas project SRP-Q98
Gas
96.4 MWOperating West Sep 2022target 2024
LIPA Summer Mobile Gens
Gas · KeySpan Energy for LIPA
96.0 MWOperating Suffolk, NYNYISO Mar 20042008
Gas project J339, Ford County
Gas
96.0 MWOperating Ford, ILMISO May 20142016
South Fork Wind Farm
Onshore wind · South Fork Wind, LLC
96.0 MWOperating Suffolk, NYNYISO Feb 2017
Springdale 1 & 2
Gas
96.0 MWOperating Allegheny, PAPJM Jan 19992000
LIPA Summer Mobile Gens
Gas · KeySpan Energy for LIPA
96.0 MWOperating NYNYISO Mar 2004
Shepherds Flat Wind Farm addition
Onshore wind · Shepherds Flat Wind, LLC
96.0 MWOperating Gilliam, ORWest Oct 2007target 2009
Hudson (Ineos/Brazoria)
Gas · Ineos
96.0 MWOperating Brazoria, TXERCOT Jan 20152020
South Fork Wind Farm
Offshore wind · South Fork Wind, LLC
96.0 MWOperating NYNYISO Feb 2017
Waterbury Generating Facility
Gas
95.7 MWOperating New Haven, CTISO-NE Feb 2007target 2009
Battery storage project 61
Battery storage
95.0 MWOperating Southeast Aug 20192021
Ginna Uprate Project
Nuclear · Constellation
95.0 MWOperating NYNYISO Jan 2004
Ginna Uprate Project
Nuclear · Constellation
95.0 MWOperating Wayne, NYNYISO Jan 20042008
Downie Ranch Solar
Solar · ConEd Development
95.0 MWOperating ERCOT May 20132015
Hydro project G032, Hancock County
Hydro
95.0 MWOperating Hancock, KYMISO Mar 20002001
Solar project J1373, White County
Solar
95.0 MWOperating White, ARMISO Apr 20192023
Onshore wind project GEN-2001-014, Caddo County
Onshore wind
94.5 MWOperating Caddo, OKSPP Apr 20012007
Granite Reliable Power
Onshore wind
94.5 MWOperating Coos, NHISO-NE Aug 2006target 2012
Onshore wind project GEN-2006-021, Barber County
Onshore wind
94.0 MWOperating Barber, KSSPP Jun 20062008
Sand Hill Peakers
Gas · Austin Energy
94.0 MWOperating ERCOT Jul 2007target 2001
San Roman Wind 1
Onshore wind · Acciona Energy
94.0 MWOperating ERCOT Jun 20112017
Texas Gulf Sulphur 1, TGS_GT01
Gas
94.0 MWOperating Wharton, TXERCOT 2022
Gas project 403, Morgan County
Gas
94.0 MWOperating Morgan, ALSoutheast Nov 2019target 2021
Notrees-1
Onshore wind · Notrees Windpower LP
93.0 MWOperating ERCOT Sep 2005target 2008
Page 34 of 96

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)