United States › Grid › Interconnection queues › Pennsylvania
GAS · PJMHaxelton Units 2-4
Haxelton Units 2-4 is a 99.0 MW gas request built and operating in the PJM interconnection queue, in Luzerne County, Pennsylvania, connecting to PPL.
Request details
- Queue ID
- D03
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PPL
- Connection point (POI)
- Harwood 69kV
- Location
- Luzerne County, Pennsylvania
- Technology
- Gas: 99.0 MW
- Total requested
- 99.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 17 April 2000
- Proposed online date
- June 2002
- Came online
- June 2002
Location
Marker shows the centre of Luzerne County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Luzerne County
- Club Ford Energy CenterSolar · 20.0 MW · agreement signed
- Club Ford Energy CenterSolar · 20.0 MW · agreement signed
- Solar project AI1-105, Luzerne CountySolar · 60.0 MW · in study
- Solar project AH2-135, Luzerne CountySolar · 50.0 MW · in study
- Solar + storage project AI2-442, Luzerne CountySolar + storage · 20.0 MW · in study
- Solar + storage project AI2-441, Luzerne CountySolar + storage · 20.0 MW · in study
- Freedom Generation PlantGas · 1,050 MW · built
- HazeltonGas · 201 MW · built
- Hunlock CreekGas · 126 MW · built
- Susquehanna #1Nuclear · 111 MW · built
- Susquehanna #2Nuclear · 107 MW · built
- Freedom Generation PlantGas · 65.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem