ONSHORE WIND Β· ERCOT

Notrees-1

Notrees-1 is a 93.0 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Sep 2005 (completed)
  2. ConsentedOct 2007 (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
07INR0005
Grid region
ERCOT (Texas)
Developer
Notrees Windpower LP
Connection point (POI)
NWF_NWF1 34.500
Technology
Wind: 93.0 MW
Total requested
93.0 MW
Study phase
IA
Queue status
Operational
Entered queue
7 September 2005
Agreement signed
16 October 2007
Proposed online date
December 2008

Location

No county location in the queue data.

Power plants in Β· Transmission lines in