United States β€Ί Grid β€Ί Interconnection queues

GAS Β· ERCOT

Sand Hill Peakers

Sand Hill Peakers is a 94.0 MW gas request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Jul 2007 (completed)
  2. ConsentedNov 2007 (completed)
  3. Construction (completed)
  4. OperatingTarget Jun 2001 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
09INR0045
Grid region
ERCOT (Texas)
Developer
Austin Energy
Connection point (POI)
SANDHSYD_SH113.800
Technology
Gas: 94.0 MW
Total requested
94.0 MW
Study phase
IA
Queue status
Operational
Entered queue
16 July 2007
Agreement signed
1 November 2007
Proposed online date
June 2001

Location

No county location in the queue data.

Power plants in Β· Transmission lines in