ONSHORE WIND · SPPOnshore wind project GEN-2012-033, Garfield County
Onshore wind project GEN-2012-033, Garfield County is a 98.8 MW onshore wind request built and operating in the SPP interconnection queue, in Garfield County, Oklahoma, connecting to OGE.
Request details
- Queue ID
- GEN-2012-033
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OGE
- Connection point (POI)
- Breckinridge 138kV
- Location
- Garfield County, Oklahoma
- Technology
- Wind: 98.8 MW
- Total requested
- 98.8 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/COMMERCIAL OPERATION
- Queue status
- Operational
- Entered queue
- 28 September 2012
- Proposed online date
- September 2015
- Came online
- September 2015
Location
Marker shows the centre of Garfield County; the queue data does not give exact sites.
Other requests in Garfield County
- Solar project GEN-2017-164, Garfield CountySolar · 250 MW · agreement signed
- Battery storage project GEN-2024-SR11, Garfield CountyBattery storage · 200 MW · agreement signed
- Battery storage project GEN-2017-178, Garfield CountyBattery storage · 52.0 MW · agreement signed
- Onshore wind project GEN-2026-PR3, Garfield CountyOnshore wind · 49.7 MW · in study
- Onshore wind project GEN-2008-013, Garfield CountyOnshore wind · 300 MW · built
- Onshore wind project GEN-2016-061, Garfield CountyOnshore wind · 251 MW · built
- Onshore wind project GEN-2016-068, Garfield CountyOnshore wind · 250 MW · built
- Onshore wind project GEN-2014-064, Garfield CountyOnshore wind · 248 MW · built
- Battery storage project GEN-2023-SR13, Garfield CountyBattery storage · 70.0 MW · built
- Onshore wind project GEN-2015-062, Garfield CountyOnshore wind · 4.5 MW · built
- Onshore wind project GEN-2008-042, Garfield CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GEN-2008-126, Garfield CountyOnshore wind · 240 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem