SOLAR Β· ERCOTDownie Ranch Solar
Downie Ranch Solar is a 95.0 MW solar request built and operating in the ERCOT interconnection queue.
Request details
- Queue ID
- 15INR0036
- Grid region
- ERCOT (Texas)
- Developer
- ConEd Development
- Connection point (POI)
- DOWNIES 138kV (5885)
- Technology
- Solar: 95.0 MW
- Total requested
- 95.0 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 14 May 2013
- Agreement signed
- 29 May 2014
- Proposed online date
- December 2015
- Came online
- December 2015