ONSHORE WIND · NYISO

South Fork Wind Farm

South Fork Wind Farm is a 96.0 MW onshore wind request built and operating in the NYISO interconnection queue, in Suffolk County, New York, connecting to LIPA.

Queue statusOperating
  1. PlanningQueued Feb 2017 (completed)
  2. ConsentedFeb 2021 (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
612
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
South Fork Wind, LLC
Connection point (POI)
East Hampton 69kV
Location
Suffolk County, New York
Technology
Wind: 96.0 MW
Total requested
96.0 MW
Study phase
SRIS, FS
Queue status
Operational
Entered queue
14 February 2017
Agreement signed
8 February 2021

Location

Marker shows the centre of Suffolk County; the queue data does not give exact sites.