United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 319

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 319 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project GEN-2017-170, Wagoner County
Battery storage
52.0 MWWithdrawn / abandoned Wagoner, OKSPP Nov 2017target 2020
Battery storage project GI-2014-6, Pueblo County
Battery storage
52.0 MWWithdrawn / abandoned Pueblo, COWest Sep 2019target 2023
Battery storage project AG2-226, Northampton County
Battery storage
52.0 MWWithdrawn / abandoned Northampton, PAPJM Mar 2021target 2022
Battery storage project GEN-2017-167, Carter County
Battery storage
52.0 MWWithdrawn / abandoned Carter, OKSPP Nov 2017target 2027
Coal project R27, Schuylkill County
Coal
52.0 MWWithdrawn / abandoned Schuylkill, PAPJM Oct 2006target 2010
Battery storage project GEN-2017-194, Shawnee County
Battery storage
52.0 MWWithdrawn / abandoned Shawnee, KSSPP Nov 2017target 2026
Brentwood Energy Storage
Battery storage · NY Power Authority
52.0 MWWithdrawn / abandoned Suffolk, NYNYISO Jul 2022
Solar project IC-551, Tattnall County
Solar
52.0 MWWithdrawn / abandoned Tattnall, GASoutheast Dec 2016
Solar project 343, Chickasaw County
Solar
52.0 MWWithdrawn / abandoned Chickasaw, MSSoutheast Apr 2018
Solar project AE2-191, Butler County
Solar
52.0 MWWithdrawn / abandoned Butler, PAPJM Mar 2019target 2022
Twig
Solar + storage
52.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Other project G076, Grant County
Other
52.0 MWWithdrawn / abandoned Grant, WIMISO Feb 2001target 2011
Pouch Energy Storage
Battery storage · NY Power Authority
52.0 MWWithdrawn / abandoned Richmond, NYNYISO Jul 2022
Onshore wind project GEN-2011-061, Dewey County
Onshore wind
52.0 MWWithdrawn / abandoned Dewey, OKSPP Dec 2011target 2013
Solar project GI-2023-13, Garfield County
Solar
52.0 MWWithdrawn / abandoned Garfield, COWest May 2023target 2026
Solar project IC-588, Lowndes County
Solar
52.0 MWWithdrawn / abandoned Lowndes, GASoutheast Jan 2017
Solar project IC-713, Macon County
Solar
52.0 MWWithdrawn / abandoned Macon, GASoutheast Jun 2018
Onshore wind project Z2-009, Luzerne County
Onshore wind
52.0 MWWithdrawn / abandoned Luzerne, PAPJM Dec 2013target 2016
Hydro project 83, Cascade County
Hydro
52.0 MWWithdrawn / abandoned Cascade, MTWest Mar 2008target 2018
Other project J636, Rapides Parish County
Other
52.0 MWWithdrawn / abandoned Rapides Parish, LAMISO May 2016target 2016
Pumpkin Valley
Battery storage
52.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Battery storage project GEN-2017-192, Osage County
Battery storage
52.0 MWWithdrawn / abandoned Osage, KSSPP Nov 20172025
Battery storage project GEN-2017-169, Mcclain County
Battery storage
52.0 MWWithdrawn / abandoned Mcclain, OKSPP Nov 2017target 2027
Solar project GI-2016-31, Morgan County
Solar
51.8 MWWithdrawn / abandoned Morgan, COWest Dec 2016target 2019
Solar project GI-2016-28, Mesa County
Solar
51.8 MWWithdrawn / abandoned Mesa, COWest Nov 2016target 2019
Solar project GI-2016-32, Arapahoe County
Solar
51.8 MWWithdrawn / abandoned Arapahoe, COWest Dec 2016target 2019
Freight Energy Storage
Battery storage
51.8 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2025
Solar project 569234, Johnston County
Solar
51.7 MWWithdrawn / abandoned Johnston, NCSoutheast Jun 2022
Battery Storage
Battery storage
51.7 MWWithdrawn / abandoned New London, CTISO-NE May 2022target 2025
Quail Run Storage System
Battery storage · Quail Run Energy Partners, LP
51.6 MWWithdrawn / abandoned Ector, TXERCOT Feb 2021target 2026
Coal project G34, Schuylkill County
Coal
51.6 MWWithdrawn / abandoned Schuylkill, PAPJM Jul 2001
Kobernat Storage
Battery storage · BT Kobernat Solar, LLC
51.5 MWWithdrawn / abandoned Starr, TXERCOT Feb 2024target 2026
Solar project GEN-2015-075, Hockley County
Solar
51.5 MWWithdrawn / abandoned Hockley, TXSPP Sep 2015target 2018
Solar
Solar
51.5 MWWithdrawn / abandoned Somerset, MEISO-NE Sep 2023target 2027
La Media
Battery storage
51.5 MWWithdrawn / abandoned Orange, CACAISO Apr 2023target 2029
Belding 2 Batt
Other · Triple Butte II LLC
51.5 MWWithdrawn / abandoned Pecos, TXERCOT Mar 2020target 2024
East End Energy Storage Center
Battery storage · sPower Development Company, LLC
51.5 MWWithdrawn / abandoned Suffolk, NYNYISO Apr 2020
Solar
Solar
51.4 MWWithdrawn / abandoned Hancock, MEISO-NE Feb 2021target 2024
Goal Line Reliability
Battery storage
51.4 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2026
Columbus Storage
Battery storage · EDP Renewables North America LLC
51.3 MWWithdrawn / abandoned ERCOT Aug 2021target 2026
Solar project GEN-2015-084, Harmon County
Solar
51.3 MWWithdrawn / abandoned Harmon, OKSPP Sep 2015target 2018
Bruin Solar
Solar
51.3 MWWithdrawn / abandoned Fresno, CACAISO May 2017target 2020
Tierra Del Oro
Solar
51.2 MWWithdrawn / abandoned Kern, CACAISO May 2016target 2020
Onshore wind project 172, Owyhee County
Onshore wind
51.2 MWWithdrawn / abandoned Owyhee, IDWest Jul 2006target 2008
Apollo Solar
Solar
51.2 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2013
Petrel Storage
Battery storage
51.1 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2024
Southern Star Storage SLF
Battery storage · Southern Star Solar Project, LLC
51.1 MWWithdrawn / abandoned ERCOT Mar 2025target 2029
Solar project AF2-145, Lycoming County
Solar
51.0 MWWithdrawn / abandoned Lycoming, PAPJM Mar 2020target 2021
M&G Resins Corpus Christi
Gas · M&G Resins USA, LLC
51.0 MWWithdrawn / abandoned ERCOT Jan 2014target 2015
Suffolk Storage
Battery storage
51.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2019target 2021
Page 319 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)