πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Maine

SOLAR Β· ISO-NE

Solar

Solar is a 51.5 MW solar request withdrawn in the ISO-NE interconnection queue, in Somerset County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2023 (completed)
  2. Withdrawn / abandonedDec 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1445
Grid region
ISO-NE (New England)
Connection point (POI)
The CMP 115 kV Chase Pond substation being built on Section 222.
Location
Somerset County, Maine
Technology
Solar: 51.5 MW
Total requested
51.5 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
21 September 2023
Proposed online date
December 2027
Withdrawn
December 2023

Location

Marker shows the centre of Somerset County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in Somerset County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem