United States › Grid › Interconnection queues › Maine

ONSHORE WIND · ISO-NE

Western Maine Wind Project

Western Maine Wind Project is a 58.8 MW onshore wind request built and operating in the ISO-NE interconnection queue, in Somerset County, Maine.

Queue statusOperating
  1. PlanningQueued May 2020 (completed)
  2. ConsentedJan 2023 (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
1028
Grid region
ISO-NE (New England)
Connection point (POI)
CMP 115 kV Section 222 - coordinates 45° 9'30.90"N, 69°51'1.40"W
Location
Somerset County, Maine
Technology
Wind: 58.8 MW
Total requested
58.8 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Operational
Entered queue
28 May 2020
Agreement signed
23 January 2023
Proposed online date
December 2024

Location

Marker shows the centre of Somerset County; the queue data does not give exact sites.

Power plants in Maine · Transmission lines in Maine

Other requests in Somerset County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem