United States β€Ί Grid β€Ί Interconnection queues β€Ί Maine

ONSHORE WIND Β· ISO-NE

Wind

Wind is a 93.6 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Somerset County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2016 (completed)
  2. Withdrawn / abandonedApr 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
621
Grid region
ISO-NE (New England)
Connection point (POI)
CMP Section 3023 345 kV line (via Johnson Mountain substation)
Location
Somerset County, Maine
Technology
Wind: 93.6 MW
Total requested
93.6 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
17 October 2016
Proposed online date
January 2020
Withdrawn
April 2018

Location

Marker shows the centre of Somerset County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in Somerset County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem