Queue requests in study in Texas — page 30

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,486351.5 GW
Active in queue476.4 GW2,094 requests
Agreement signed124.6 GW606 requests
Withdrawn917184.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,486 requests · page 30 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Kennedy Storage
Solar + storage · Kennedy Bypass Solar LLC
25.3 MWIn study Navarro, TXERCOT Jul 2022target 2028
Burro Loco Energy Storage
Battery storage · VESI
25.1 MWIn study Cameron, TXERCOT Jul 2022target 2026
Fluorite Solar
Solar
25.0 MWPaused / redesign Uvalde, TXERCOT Aug 2017
Knickerbocker Storage
Other · Knickerbocker Solar LLC
25.0 MWPaused / redesign Tom Green, TXERCOT Dec 2019target 2028
CPS Energy AvR1CT2 Rotor Replacement
Gas · CPS Energy
23.2 MWIn study Bexar, TXERCOT Oct 2023target 2025
Brazos Wind Repower
Onshore wind · BRAZOS WIND VENTURES, LLC
22.4 MWIn study Scurry, TXERCOT Dec 2020target 2025
Brandon
Gas
21.0 MWPaused / redesign Lubbock, TXERCOT Sep 2018target 2021
Sparkl BESS
Battery storage
20.0 MWPaused / redesign Guadalupe, TXERCOT Dec 2019
Basalt Solar
Solar
20.0 MWPaused / redesign Uvalde, TXERCOT Jul 2017
Shannon Wind Repower
Onshore wind · Shannon Wind, LLC
18.5 MWIn study Archer, TXERCOT Feb 2024target 2027
Buzzi Maryneal Wind Project
Onshore wind · Buzzi Unicem USA
18.0 MWIn study Nolan, TXERCOT Oct 2023target 2026
Midlothian 4 repower
Gas · MIDLOTHIAN ENERGY, LLC
18.0 MWIn study Ellis, TXERCOT Apr 2021target 2026
Midlothian Unit 2 repower
Gas · MIDLOTHIAN ENERGY, LLC
18.0 MWIn study Ellis, TXERCOT Jan 2021target 2026
Hays Energy Unit 2 Repower
Gas · HAYS ENERGY, LLC
18.0 MWIn study Hays, TXERCOT Feb 2022target 2026
Hays Energy Unit 3 Repower
Gas · HAYS ENERGY, LLC
18.0 MWIn study Hays, TXERCOT Oct 2020target 2026
Midlothian Unit 3 repower
Gas · MIDLOTHIAN ENERGY, LLC
18.0 MWIn study Ellis, TXERCOT May 2021target 2026
Clutch City Storage I SLF
Battery storage
16.6 MWPaused / redesign Galveston, TXERCOT Nov 2022
Texas Gulf Sulphur Repower
Gas
16.1 MWPaused / redesign Wharton, TXERCOT Jul 2023
Stephens Ranch Wind Repower
Onshore wind · Stephens Ranch Wind Energy, LLC
12.4 MWIn study Borden, TXERCOT Jun 2023target 2027
Clutch City Storage II SLF
Battery storage
11.3 MWPaused / redesign Brazoria, TXERCOT Feb 2023
CPS AvR CT1 Rotor Replacement
Gas · CPS Energy
11.3 MWIn study Bexar, TXERCOT Oct 2022target 2025
Panther Creek 1 Repower
Onshore wind · Panther Creek Wind Farm I&II, LLC
11.0 MWIn study Glasscock, TXERCOT Jun 2023target 2026
Mirage
Gas
11.0 MWPaused / redesign Harris, TXERCOT Feb 2015
Wildhorse POD Solar
Solar · Highpeak Solar, LLC
10.0 MWPaused / redesign Howard, TXERCOT Oct 2023target 2026
Harris Spencer BESS
Other · Harris Spencer BESS, LLC
10.0 MWPaused / redesign Harris, TXERCOT Mar 20232025
Pleasanton BESS
Other
10.0 MWPaused / redesign Atascosa, TXERCOT
Juno Solar 3
Solar · SE JUNO LLC
10.0 MWPaused / redesign Borden, TXERCOT target 2023
Blue Summit repower
Onshore wind
9.9 MWPaused / redesign Wilbarger, TXERCOT Jan 2018
Panther Creek 2 Repower
Onshore wind · Panther Creek Wind Farm I&II, LLC
8.0 MWIn study Glasscock, TXERCOT Jun 2023target 2026
Roadrunner Crossing Wind (Uprate)
Wind + storage · Roadrunner Wind, LLC
3.3 MWIn study Eastland, TXERCOT Dec 2025target 2026
Ashra Storage SLF
Solar + storage · Ashra Solar, LLC
1.6 MWIn study Uvalde, TXERCOT Apr 2025target 2028
Kickstart Energy Storage IV
Battery storage · Kickstart Infrastructure LLC
1.4 MWIn study Ellis, TXERCOT Mar 2025target 2029
Kickstart Energy Storage III
Battery storage · Kickstart Infrastructure LLC
1.4 MWIn study Ellis, TXERCOT Mar 2025target 2029
Kickstart Energy Storage I
Battery storage · Kickstart Infrastructure LLC
1.4 MWIn study Ellis, TXERCOT Mar 2025target 2029
Kickstart Energy Storage II
Battery storage · Kickstart Infrastructure LLC
1.4 MWIn study Ellis, TXERCOT Mar 2025target 2029
Giga Austin Solar
Solar · GIGA TEXAS ENERGY LLC
-53.3 MWIn study Travis, TXERCOT Jul 2022target 2025
Page 30 of 30

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)