United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Projects with signed interconnection agreements in the USA (2017 requests) โ€” page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown18232.8 GW
Active in queue51.0 GW292 requests
Agreement signed32.8 GW182 requests
Withdrawn1,258161.7 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

182 requests ยท page 3 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Marion County Solar Project
Solar
100 MWAgreement signed Marion, OHPJM Apr 2017target 2025
Onshore wind project GEN-2017-215, Ward County
Onshore wind
100 MWAgreement signed Ward, NDSPP Nov 2017target 2030
Onshore wind project GEN-2017-214, Ward County
Onshore wind
100 MWAgreement signed Ward, NDSPP Nov 2017target 2030
Battery storage project Company HS, Washoe County
Battery storage
100 MWAgreement signed Washoe, NVWest Sep 2017target 2027
Southwest Michigan Energy Center
Solar
100 MWAgreement signed Van Buren, MIPJM Dec 2017target 2027
Solar project Q254, Pinal County
Solar
100 MWAgreement signed Pinal, AZWest Mar 2017target 2022
Solar project 313, Monroe County
Solar
100 MWAgreement signed Monroe, MSSoutheast May 2017target 2026
Solar project 49, Kittitas County
Solar
100 MWAgreement signed Kittitas, WAWest Apr 2017target 2027
Solar project Company HL, Lander County
Solar
100 MWAgreement signed Lander, NVWest Mar 2017target 2023
Firefly Solar
Solar
96.0 MWAgreement signed Pittsylvania, VAPJM Dec 2017target 2026
Solar project IA-PNM-2017-15, San Juan County
Solar
95.6 MWAgreement signed San Juan, NMWest Oct 2017target 2022
Firefly Solar
Solar
95.0 MWAgreement signed Pittsylvania, VAPJM Dec 2017target 2026
Solar project LGE-GIS-2017-002, Lyon County
Solar
86.0 MWAgreement signed Lyon, KYSoutheast Mar 2017target 2024
Solar project GEN-2017-023, Choctaw County
Solar
85.0 MWAgreement signed Choctaw, OKSPP May 2017target 2026
Sand Hill C
Onshore wind
84.3 MWAgreement signed Alameda, CACAISO May 2017target 2027
Solar + storage project 907, Klamath County
Solar + storage ยท Fresh Air Energy II, LLC
80.0 MWAgreement signed Klamath, ORWest Jul 2017target 2030
Gonzaga Wind Farm
Onshore wind
80.0 MWAgreement signed Merced, CACAISO May 2017target 2026
Angelina Solar I
Solar
80.0 MWAgreement signed Preble, OHPJM Mar 2017target 2027
Sumac Solar
Solar
80.0 MWAgreement signed Bertie, NCPJM Jun 2017target 2028
Solar + storage project 906, Klamath County
Solar + storage ยท Fresh Air Energy II, LLC
80.0 MWAgreement signed Klamath, ORWest Jul 2017target 2028
Solar project Company HP, Lander County
Solar
79.0 MWAgreement signed Lander, NVWest Sep 2017target 2027
Macadamia Solar
Solar
75.0 MWAgreement signed Washington, NCPJM Aug 2017target 2028
Onshore wind project GEN-2017-105, Burt County
Onshore wind
75.0 MWAgreement signed Burt, NESPP Jul 2017target 2026
Solar project 846, Tooele County
Solar ยท Horseshoe Solar, LLC
75.0 MWAgreement signed Tooele, UTWest Jan 2017target 2023
Sweet Sue Solar
Solar
74.0 MWAgreement signed King William, VAPJM Sep 2017target 2026
Solar + storage project 333, Shelby County
Solar + storage
74.0 MWAgreement signed Shelby, TNSoutheast Oct 2017target 2024
Solar project GEN-2017-057, Caddo Parish County
Solar
72.5 MWAgreement signed Caddo Parish, LASPP May 20172025
Solar project GEN-2017-231, Franklin County
Solar
72.5 MWAgreement signed Franklin, ARSPP Nov 2017target 2027
Solar project GEN-2017-230, Lincoln County
Solar
72.5 MWAgreement signed Lincoln, OKSPP Nov 2017target 2027
Solar project GEN-2017-074, Mayes County
Solar
72.5 MWAgreement signed Mayes, OKSPP May 20172025
Solar project GEN-2017-073, Mayes County
Solar
72.5 MWAgreement signed Mayes, OKSPP May 20172025
Solar project 48968, Chester County
Solar
69.8 MWAgreement signed Chester, SCSoutheast Nov 2017target 2027
Solar project GEN-2017-022, Wilson County
Solar
65.0 MWAgreement signed Wilson, KSSPP May 2017target 2027
Solar project 314, Monroe County
Solar
60.0 MWAgreement signed Monroe, MSSoutheast May 2017target 2021
Camino Solar
Solar + storage
58.3 MWAgreement signed Kern, CACAISO May 2017target 2027
Solar project GI-2017-5, Park County
Solar
54.3 MWAgreement signed Park, COWest Jan 2017target 2019
Solar project GEN-2017-072, Payne County
Solar
52.2 MWAgreement signed Payne, OKSPP May 20172025
Solar project GEN-2017-232, Bryan County
Solar
52.2 MWAgreement signed Bryan, OKSPP Nov 2017target 2026
Solar project J791, Lamar County
Solar
52.0 MWAgreement signed Lamar, MSMISO Apr 2017target 2020
Battery storage project GEN-2017-178, Garfield County
Battery storage
52.0 MWAgreement signed Garfield, OKSPP Nov 20172025
Solar project GEN-2017-173, Comanche County
Solar
50.0 MWAgreement signed Comanche, OKSPP Nov 2017target 2027
Solar project IA-PNM-2017-07, Sandoval County
Solar ยท NM Renewable Development
50.0 MWAgreement signed Sandoval, NMWest Jan 2017target 2022
Solar project JEA-Q007-PV, Duval County
Solar
50.0 MWAgreement signed Duval, FLSoutheast Dec 2017target 2026
Greenwood Solar
Solar
50.0 MWAgreement signed Culpeper, VAPJM Sep 2017target 2027
Staley Solar
Solar
50.0 MWAgreement signed Kankakee, ILPJM Mar 2017target 2027
Solar project GEN-2017-172, Comanche County
Solar
50.0 MWAgreement signed Comanche, OKSPP Nov 2017target 2027
Battery storage project Company 155, Clark County
Battery storage
50.0 MWAgreement signed Clark, NVWest Sep 2017target 2023
NMRD Data Center IV
Solar
50.0 MWAgreement signed Santa Fe, NMWest Jan 2017target 2022
Solar project IA-PNM-2017-06, Sandoval County
Solar ยท NM Renewable Development
50.0 MWAgreement signed Sandoval, NMWest Jan 2017target 2022
Eaton OH Solar
Solar
49.9 MWAgreement signed Preble, OHPJM Feb 2017target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)