United States › Grid › Interconnection queues › Mississippi
SOLAR · SOUTHEASTSolar project 313, Monroe County
Solar project 313, Monroe County is a 100 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Monroe County, Mississippi, connecting to Tennessee Valley Authority.
Queue statusConsented
- PlanningQueued May 2017 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 313
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Tennessee Valley Authority
- Connection point (POI)
- Stateline - West Point 161-kV TL
- Location
- Monroe County, Mississippi
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 23 May 2017
- Proposed online date
- September 2026
Location
Marker shows the centre of Monroe County; the queue data does not give exact sites.
Power plants in Mississippi · Transmission lines in Mississippi
Other requests in Monroe County
- Solar project 314, Monroe CountySolar · 60.0 MW · agreement signed
- Solar + storage project 671, Monroe CountySolar + storage · 75.0 MW · in study
- Solar + storage project 647, Monroe CountySolar + storage · 440 MW · withdrawn
- Solar project 602, Monroe CountySolar · 240 MW · withdrawn
- Solar project 606, Monroe CountySolar · 200 MW · withdrawn
- Solar + storage project 443, Monroe CountySolar + storage · 160 MW · withdrawn
- Solar project 553, Monroe CountySolar · 150 MW · withdrawn
- Solar project 249, Monroe CountySolar · 119 MW · withdrawn
- Solar project 250, Monroe CountySolar · 67.0 MW · withdrawn
- Solar project 252, Monroe CountySolar · 67.0 MW · withdrawn
- Solar project 315, Monroe CountySolar · 66.0 MW · withdrawn
- Solar project 550, Monroe CountySolar · 65.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem