🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Minnesota

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Minnesota — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown48280.5 GW
Active in queue28.4 GW155 requests
Agreement signed309 MW9 requests
Withdrawn48280.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

482 requests · page 3 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1531, Sherburne County
Solar
200 MWWithdrawn / abandoned Sherburne, MNMISO Jun 2020target 2023
Onshore wind project J141, Fillmore County
Onshore wind
200 MWWithdrawn / abandoned Fillmore, MNMISO Nov 2009target 2012
Nuclear project J123, Goodhue County
Nuclear
200 MWWithdrawn / abandoned Goodhue, MNMISO Apr 2010target 2011
Onshore wind project J876, Faribault County
Onshore wind
200 MWWithdrawn / abandoned Faribault, MNMISO Jun 2017target 2020
Onshore wind project H083, Lyon County
Onshore wind
200 MWWithdrawn / abandoned Lyon, MNMISO Jun 2008target 2015
Solar project J2065, Pipestone County
Solar
200 MWWithdrawn / abandoned Pipestone, MNMISO Jul 2021target 2024
Onshore wind project J720, Jackson County
Onshore wind
200 MWWithdrawn / abandoned Jackson, MNMISO Jun 2017target 2021
Onshore wind project G377, St. Louis County
Onshore wind
200 MWWithdrawn / abandoned St. Louis, MNMISO Nov 2003target 2004
Onshore wind project J063, Clearwater County
Onshore wind
200 MWWithdrawn / abandoned Clearwater, MNMISO Aug 2009target 2013
Onshore wind project G991, Fillmore County
Onshore wind
200 MWWithdrawn / abandoned Fillmore, MNMISO Apr 2011target 2008
Solar project J935, Hubbard County
Solar
200 MWWithdrawn / abandoned Hubbard, MNMISO Jun 2017target 2020
Solar project J1149, Yellow Medicine County
Solar
200 MWWithdrawn / abandoned Yellow Medicine, MNMISO Mar 2018target 2021
Onshore wind project G163, Murray County
Onshore wind
200 MWWithdrawn / abandoned Murray, MNMISO Dec 2001target 2003
Solar project J2037, Olmsted County
Solar
200 MWWithdrawn / abandoned Olmsted, MNMISO Jul 2021target 2024
Onshore wind project J726, Cottonwood County
Onshore wind
200 MWWithdrawn / abandoned Cottonwood, MNMISO Jun 2017target 2019
Battery storage project J3526, Goodhue County
Battery storage
200 MWWithdrawn / abandoned Goodhue, MNMISO Apr 2024target 2030
Onshore wind project G183, Murray County
Onshore wind
200 MWWithdrawn / abandoned Murray, MNMISO Mar 2002target 2004
Gas project G351, Dakota County
Gas
200 MWWithdrawn / abandoned Dakota, MNMISO Jul 2003target 2005
Onshore wind project G772, Nobles County
Onshore wind
200 MWWithdrawn / abandoned Nobles, MNMISO Mar 2007target 2010
Onshore wind project G671, Freeborn County
Onshore wind
200 MWWithdrawn / abandoned Freeborn, MNMISO Aug 2006target 2008
Onshore wind project G669, Mower County
Onshore wind
200 MWWithdrawn / abandoned Mower, MNMISO Aug 2006target 2008
Onshore wind project G425, Jackson County
Onshore wind
200 MWWithdrawn / abandoned Jackson, MNMISO Apr 2004target 2006
Onshore wind project G429, Jackson County
Onshore wind
200 MWWithdrawn / abandoned Jackson, MNMISO May 2004target 2006
Onshore wind project J901, Redwood County
Onshore wind
200 MWWithdrawn / abandoned Redwood, MNMISO Jun 2017target 2021
Solar project J1105, Dakota County
Solar
200 MWWithdrawn / abandoned Dakota, MNMISO Mar 2018target 2020
Onshore wind project G855, Freeborn County
Onshore wind
200 MWWithdrawn / abandoned Freeborn, MNMISO Sep 2007target 2012
Solar project J1570, Rock County
Solar
200 MWWithdrawn / abandoned Rock, MNMISO Jun 2020target 2023
Battery storage project J2200, Scott County
Battery storage
200 MWWithdrawn / abandoned Scott, MNMISO Aug 2021target 2024
Solar project J3863, Itasca County
Solar
200 MWWithdrawn / abandoned Itasca, MNMISO Dec 2024target 2028
Onshore wind project J739, Lyon County
Onshore wind
200 MWWithdrawn / abandoned Lyon, MNMISO Nov 2016target 2020
Onshore wind project J725, Murray County
Onshore wind
200 MWWithdrawn / abandoned Murray, MNMISO Jun 2017target 2020
Onshore wind project J943, Lincoln County
Onshore wind
200 MWWithdrawn / abandoned Lincoln, MNMISO Jun 2017target 2020
Onshore wind project J016, Steele County
Onshore wind
200 MWWithdrawn / abandoned Steele, MNMISO Jan 2009target 2012
Onshore wind project J3705, Redwood County
Onshore wind
200 MWWithdrawn / abandoned Redwood, MNMISO Apr 2024target 2028
Gas project G352, Dakota County
Gas
200 MWWithdrawn / abandoned Dakota, MNMISO Jul 2003target 2011
Onshore wind project G890, Fillmore County
Onshore wind
200 MWWithdrawn / abandoned Fillmore, MNMISO Oct 2007target 2008
Onshore wind project G670, Faribault County
Onshore wind
200 MWWithdrawn / abandoned Faribault, MNMISO Oct 2010target 2011
Onshore wind project G961, Goodhue County
Onshore wind
200 MWWithdrawn / abandoned Goodhue, MNMISO Apr 2011target 2012
Onshore wind project J051, Jackson County
Onshore wind
200 MWWithdrawn / abandoned Jackson, MNMISO Jun 2009target 2009
Onshore wind project J761, Faribault County
Onshore wind
200 MWWithdrawn / abandoned Faribault, MNMISO Nov 2016target 2020
Onshore wind project J254, Lyon County
Onshore wind
200 MWWithdrawn / abandoned Lyon, MNMISO Sep 2012target 2014
Onshore wind project G824, Mower County
Onshore wind
200 MWWithdrawn / abandoned Mower, MNMISO Jul 2007target 2010
Onshore wind project H050, Meeker County
Onshore wind
200 MWWithdrawn / abandoned Meeker, MNMISO Jun 2008target 2011
Onshore wind project J017, Stearns County
Onshore wind
200 MWWithdrawn / abandoned Stearns, MNMISO Jan 2009target 2012
Solar project J1524, Pipestone County
Solar
200 MWWithdrawn / abandoned Pipestone, MNMISO Jun 2020target 2023
Onshore wind project G262, Jackson County
Onshore wind
200 MWWithdrawn / abandoned Jackson, MNMISO Oct 2002target 2007
Battery storage project J3369, Scott County
Battery storage
200 MWWithdrawn / abandoned Scott, MNMISO Mar 2024target 2028
Solar project J1847, Mower County
Solar
200 MWWithdrawn / abandoned Mower, MNMISO Aug 2021target 2024
Onshore wind project H072, Mcleod County
Onshore wind
200 MWWithdrawn / abandoned Mcleod, MNMISO Jun 2008target 2011
Solar project J2022, Mower County
Solar
200 MWWithdrawn / abandoned Mower, MNMISO Oct 2021target 2024
Page 3 of 10

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)