United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project G772, Nobles County

Onshore wind project G772, Nobles County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Nobles County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2007 (completed)
  2. Withdrawn / abandonedMay 2011 (project stopped here)
  3. ConsentedMay 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G772
Grid region
MISO (Midcontinent)
Connection point (POI)
Xel Split Rock - Lakefield 345 kV
Location
Nobles County, Minnesota
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
23 March 2007
Agreement signed
4 May 2011
Proposed online date
January 2010
Withdrawn
May 2011

Location

Marker shows the centre of Nobles County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Nobles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem