United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project G262, Jackson County

Onshore wind project G262, Jackson County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Jackson County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2002 (completed)
  2. Withdrawn / abandonedSep 2004 (project stopped here)
  3. ConsentedSep 2004 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G262
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Jackson County, Minnesota
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
22 October 2002
Agreement signed
9 September 2004
Proposed online date
May 2007
Withdrawn
September 2004

Location

Marker shows the centre of Jackson County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Jackson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem