ONSHORE WIND Β· MISOOnshore wind project J876, Faribault County
Onshore wind project J876, Faribault County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Faribault County, Minnesota, connecting to ITC MIDWEST.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2017 (completed)
- Withdrawn / abandonedJul 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J876
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- Huntley 345kV sub
- Location
- Faribault County, Minnesota
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 16 June 2017
- Proposed online date
- September 2020
- Withdrawn
- July 2019
Location
Marker shows the centre of Faribault County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Faribault County
- Solar project J1503, Faribault CountySolar Β· 150 MW Β· in study
- Solar + storage project J1572, Faribault CountySolar + storage Β· 150 MW Β· in study
- Solar project J1504, Faribault CountySolar Β· 150 MW Β· in study
- Onshore wind project G358, Faribault CountyOnshore wind Β· 36.0 MW Β· built
- Battery storage project J2419, Faribault CountyBattery storage Β· 300 MW Β· withdrawn
- Onshore wind project G670, Faribault CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project J761, Faribault CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project J927, Faribault CountyOnshore wind Β· 100 MW Β· withdrawn
- Solar project J1228, Faribault CountySolar Β· 100 MW Β· withdrawn
- Solar project J2420, Faribault CountySolar Β· 95.0 MW Β· withdrawn
- Other project G109, Faribault CountyOther Β· 50.0 MW Β· withdrawn
- Solar project J1008, Faribault CountySolar Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem