United States › Grid › Interconnection queues › Minnesota
ONSHORE WIND · MISOOnshore wind project G358, Faribault County
Onshore wind project G358, Faribault County is a 36.0 MW onshore wind request built and operating in the MISO interconnection queue, in Faribault County, Minnesota.
Request details
- Queue ID
- G358
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Winco - Winnebago 161kV
- Location
- Faribault County, Minnesota
- Technology
- Wind: 36.0 MW
- Total requested
- 36.0 MW
- Study phase
- Network Upgrade
- Queue status
- Operational
- Entered queue
- 30 September 2003
- Agreement signed
- 24 January 2007
- Proposed online date
- September 2003
- Came online
- September 2003
Location
Marker shows the centre of Faribault County; the queue data does not give exact sites.
Other requests in Faribault County
- Solar project J1503, Faribault CountySolar · 150 MW · in study
- Solar + storage project J1572, Faribault CountySolar + storage · 150 MW · in study
- Solar project J1504, Faribault CountySolar · 150 MW · in study
- Battery storage project J2419, Faribault CountyBattery storage · 300 MW · withdrawn
- Onshore wind project J876, Faribault CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project G670, Faribault CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J761, Faribault CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J927, Faribault CountyOnshore wind · 100 MW · withdrawn
- Solar project J1228, Faribault CountySolar · 100 MW · withdrawn
- Solar project J2420, Faribault CountySolar · 95.0 MW · withdrawn
- Other project G109, Faribault CountyOther · 50.0 MW · withdrawn
- Solar project J1008, Faribault CountySolar · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem