🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Minnesota

ONSHORE WIND · MISO

Onshore wind project G358, Faribault County

Onshore wind project G358, Faribault County is a 36.0 MW onshore wind request built and operating in the MISO interconnection queue, in Faribault County, Minnesota.

Queue statusOperating
  1. PlanningQueued Sep 2003 (completed)
  2. ConsentedJan 2007 (completed)
  3. Construction (completed)
  4. OperatingSep 2003 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G358
Grid region
MISO (Midcontinent)
Connection point (POI)
Winco - Winnebago 161kV
Location
Faribault County, Minnesota
Technology
Wind: 36.0 MW
Total requested
36.0 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
30 September 2003
Agreement signed
24 January 2007
Proposed online date
September 2003
Came online
September 2003

Location

Marker shows the centre of Faribault County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Faribault County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem