Solar project J2037, Olmsted County

Solar project J2037, Olmsted County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Olmsted County, Minnesota, connecting to SOUTHERN MINNESOTA MUNICIPAL POWER AGENCY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2021 (completed)
  2. Withdrawn / abandonedNov 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2037
Grid region
MISO (Midcontinent)
Utility / transmission owner
SOUTHERN MINNESOTA MUNICIPAL POWER AGENCY
Connection point (POI)
Byron 345 kV Substation
Location
Olmsted County, Minnesota
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3
Queue status
Withdrawn
Entered queue
20 July 2021
Proposed online date
October 2024
Withdrawn
November 2021

Location

Marker shows the centre of Olmsted County; the queue data does not give exact sites.