🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 283

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 283 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 956958, Nash County
Solar
78.3 MWWithdrawn / abandoned Nash, NCSoutheast Jun 2024
Solar project 564638, Nash County
Solar
78.3 MWWithdrawn / abandoned Nash, NCSoutheast Jun 2022
Solar project 30708, Nash County
Solar
78.3 MWWithdrawn / abandoned Nash, NCSoutheast Feb 2019
Solar project 910009, Nash County
Solar
78.3 MWWithdrawn / abandoned Nash, NCSoutheast Sep 2023
Solar project 738, Crook County
Solar
78.3 MWWithdrawn / abandoned Crook, ORWest Apr 2016target 2018
Solar project IC-693, Dale County
Solar
78.2 MWWithdrawn / abandoned Dale, ALSoutheast Apr 2018
Coso Solar 1
Solar
78.2 MWWithdrawn / abandoned Inyo, CACAISO May 2016target 2018
Solar + storage project J2137, Ohio County
Solar + storage
78.2 MWWithdrawn / abandoned Ohio, KYMISO Oct 2021target 2024
Onshore wind project GEN-2016-016, Edwards County
Onshore wind
78.2 MWWithdrawn / abandoned Edwards, KSSPP Mar 20162023
Prattsburgh Wind Farm
Onshore wind · ECOGEN, LLC
78.2 MWWithdrawn / abandoned Yates, NYNYISO May 2002
Onshore wind project 470, Tooele County
Onshore wind
78.2 MWWithdrawn / abandoned Tooele, UTWest Feb 2013target 2014
Palmas Altas Wind
Onshore wind · Cielo Wind Services
78.0 MWWithdrawn / abandoned ERCOT May 2009target 2050
Mooncrest
Battery storage
78.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Solar project IC-452, Dale County
Solar
78.0 MWWithdrawn / abandoned Dale, ALSoutheast Apr 2016
Gas Turbine
Other
78.0 MWWithdrawn / abandoned New Haven, CTISO-NE Dec 2006target 2011
Solar project AE2-179, Pike County
Solar
78.0 MWWithdrawn / abandoned Pike, OHPJM Mar 2019target 2021
Onshore wind project AC2-003, Botetourt County
Onshore wind
78.0 MWWithdrawn / abandoned Botetourt, VAPJM Nov 2016target 2023
Little Falls Solar
Solar · Hodson Energy Little Falls LLC
78.0 MWWithdrawn / abandoned Herkimer, NYNYISO Oct 2024
Onshore wind project 208, Big Horn County
Onshore wind · Gaelectric
78.0 MWWithdrawn / abandoned Big Horn, MTWest Mar 2008target 2012
Solar project AE2-205, Cumberland County
Solar
78.0 MWWithdrawn / abandoned Cumberland, NJPJM Mar 2019target 2022
Battery storage project J1869, Winn Parish County
Battery storage
78.0 MWWithdrawn / abandoned Winn Parish, LAMISO Aug 2021target 2024
Solar project 1129, Millard County
Solar
78.0 MWWithdrawn / abandoned Millard, UTWest Apr 2019target 2022
Solar project IC-363, Oglethorpe County
Solar
78.0 MWWithdrawn / abandoned Oglethorpe, GASoutheast Apr 2014
Solar project AD1-117, Ogle County
Solar
78.0 MWWithdrawn / abandoned Ogle, ILPJM Sep 2017target 2020
Onshore wind project 168, Big Horn County
Onshore wind · Evergreen Wind Power Partner, LLC
78.0 MWWithdrawn / abandoned Big Horn, MTWest Oct 2007target 2012
West Earl
Gas
78.0 MWWithdrawn / abandoned Lancaster, PAPJM Nov 1999target 2004
Solar project IC-596, Marengo County
Solar
78.0 MWWithdrawn / abandoned Marengo, ALSoutheast Feb 2017
Solar project IC-595, Marengo County
Solar
78.0 MWWithdrawn / abandoned Marengo, ALSoutheast Feb 2017
Solar project IC-899, Stone County
Solar
78.0 MWWithdrawn / abandoned Stone, MSSoutheast Aug 2020target 2024
Roaring Brook Wind
Onshore wind · PPM Roaring Brook, LLC / PPM
78.0 MWWithdrawn / abandoned Lewis, NYNYISO Jul 2005
Solar project J917, Liberty County
Solar
78.0 MWWithdrawn / abandoned Liberty, TXMISO Jun 2017target 2019
Solar + storage project AH2-210, St. Joseph County
Solar + storage
78.0 MWWithdrawn / abandoned St. Joseph, INPJM Mar 2022target 2025
Solar project IC-898, Stone County
Solar
78.0 MWWithdrawn / abandoned Stone, MSSoutheast Aug 2020
Chamise
Solar + storage
77.7 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2024
Nereida Solar
Solar · ABEI & INFRASTRUCTURE S.L.
77.6 MWWithdrawn / abandoned Jones, TXERCOT May 2019target 2022
Yaphank Energy Storage
Battery storage · Yaphank Energy Storage, LLC
77.6 MWWithdrawn / abandoned Suffolk, NYNYISO Dec 2019
Solar project J3608, Henry County
Solar
77.6 MWWithdrawn / abandoned Henry, INMISO Apr 2024target 2028
Onshore wind project GI-64, Sullivan County
Onshore wind
77.5 MWWithdrawn / abandoned Sullivan, MOSoutheast Feb 2018target 2020
Solar + storage project 865, Iron County
Solar + storage
77.5 MWWithdrawn / abandoned Iron, UTWest Apr 2017target 2020
Onshore wind project GI-49, Sullivan County
Onshore wind
77.5 MWWithdrawn / abandoned Sullivan, MOSoutheast Jun 2013target 2014
Solar + storage project TCS-02, Iron County
Solar + storage
77.5 MWWithdrawn / abandoned Iron, UTWest Apr 2017target 2023
Solar + storage project 864, Iron County
Solar + storage
77.5 MWWithdrawn / abandoned Iron, UTWest Apr 2017target 2020
Solar + storage project TCS-03, Iron County
Solar + storage
77.5 MWWithdrawn / abandoned Iron, UTWest Apr 2017target 2023
Onshore wind project GI-56, Sullivan County
Onshore wind
77.5 MWWithdrawn / abandoned Sullivan, MOSoutheast May 2016target 2018
Solar project AF1-170, Crawford County
Solar
77.5 MWWithdrawn / abandoned Crawford, PAPJM Sep 2019target 2023
Wild Hill Solar
Solar
77.5 MWWithdrawn / abandoned Jefferson, WVPJM Mar 2018target 2024
Solar project AG2-190, Carroll County
Solar
77.4 MWWithdrawn / abandoned Carroll, VAPJM Feb 2021target 2024
Solar project Q59, Kern County
Solar
77.0 MWWithdrawn / abandoned Kern, CAWest Mar 2017target 2020
South Suffolk Storage
Battery storage · South Suffolk Energy Storage, LLC
77.0 MWWithdrawn / abandoned Suffolk, NYNYISO Aug 2024
Solar + storage project IA-PNM-2019-03, Bernalillo County
Solar + storage
77.0 MWWithdrawn / abandoned Bernalillo, NMWest Apr 2019target 2022
Page 283 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)