OTHER Β· ISO-NE

Gas Turbine

Gas Turbine is a 78.0 MW other request withdrawn in the ISO-NE interconnection queue, in New Haven County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2006 (completed)
  2. Withdrawn / abandonedMay 2009 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
186
Grid region
ISO-NE (New England)
Connection point (POI)
CL&P Shepaug 115 kV substation
Location
New Haven County, Connecticut
Technology
Oil: 78.0 MW
Total requested
78.0 MW
Service type
Other
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
1 December 2006
Proposed online date
December 2011
Withdrawn
May 2009

Location

No county location in the queue data.

Power plants in Connecticut Β· Transmission lines in Connecticut

Other requests in New Haven County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem