🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

BATTERY STORAGE · NYISO

Yaphank Energy Storage

Yaphank Energy Storage is a 77.6 MW battery storage request withdrawn in the NYISO interconnection queue, in Suffolk County, New York, connecting to LIPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2019 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
965
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
Yaphank Energy Storage, LLC
Connection point (POI)
William Floyd - Brookhaven 69kV
Location
Suffolk County, New York
Technology
Battery: 77.6 MW
Total requested
77.6 MW
Queue status
Withdrawn
Entered queue
21 December 2019

Location

Marker shows the centre of Suffolk County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Suffolk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem