SOLAR Β· MISO

Solar project J917, Liberty County

Solar project J917, Liberty County is a 78.0 MW solar request withdrawn in the MISO interconnection queue, in Liberty County, Texas, connecting to Entergy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandonedJan 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J917
Grid region
MISO (Midcontinent)
Utility / transmission owner
Entergy
Connection point (POI)
Tarkington - New Long John 138kV line tap
Location
Liberty County, Texas
Technology
Solar: 78.0 MW
Total requested
78.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
16 June 2017
Proposed online date
November 2019
Withdrawn
January 2019

Location

Marker shows the centre of Liberty County; the queue data does not give exact sites.