Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,063551.8 GW
Active in queue298.6 GW1,249 requests
Agreement signed34.6 GW168 requests
Withdrawn2,063551.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,063 requests ยท page 24 of 42
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 138, King County
Battery storage
175 MWWithdrawn / abandoned King, WAWest May 2023target 2025
Solar project GEN-2023-154, Hand County
Solar
175 MWWithdrawn / abandoned Hand, SDSPP Oct 2023target 2029
Solar + storage project GEN-2022-211, Lancaster County
Solar + storage
175 MWWithdrawn / abandoned Lancaster, NESPP Mar 2023target 2027
Battery storage project GEN-2023-168, Oklahoma County
Battery storage
175 MWWithdrawn / abandoned Oklahoma, OKSPP Oct 2023target 2028
Battery storage project GEN-2023-082, Brookings County
Battery storage
175 MWWithdrawn / abandoned Brookings, SDSPP Oct 2023target 2029
Solar + storage project GI-2023-5, Pueblo County
Solar + storage
175 MWWithdrawn / abandoned Pueblo, COWest May 2023target 2028
Battery storage project IC-1143, Floyd County
Battery storage
175 MWWithdrawn / abandoned Floyd, GASoutheast May 2023
Onshore wind project GEN-2023-192, Lamoure County
Onshore wind
175 MWWithdrawn / abandoned Lamoure, NDSPP Oct 2023target 2030
Battery Storage
Battery storage
172 MWWithdrawn / abandoned Hampden, MAISO-NE Jun 2023target 2027
Saltgrass
Battery storage
171 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2023target 2028
Basecamp BESS
Battery storage ยท RWE Solar Development
170 MWWithdrawn / abandoned Chautauqua, NYNYISO Jul 2023
Solar + storage project GI-2023-11, Saguache County
Solar + storage
170 MWWithdrawn / abandoned Saguache, COWest May 2023target 2026
Battery storage project GEN-2023-159, Bailey County
Battery storage
170 MWWithdrawn / abandoned Bailey, TXSPP Oct 2023target 2029
Solar project IC-1138, Monroe County
Solar
170 MWWithdrawn / abandoned Monroe, GASoutheast May 2023
Solar project G1033, Fremont County
Solar
170 MWWithdrawn / abandoned Fremont, IDWest Nov 2023target 2028
MegaCharge BESS
Other ยท SMT Dallas II LLC
169 MWWithdrawn / abandoned Dallas, TXERCOT Jul 2023target 2026
Solar project GI-119, St Clair County
Solar
166 MWWithdrawn / abandoned St Clair, MOSoutheast Aug 2023target 2027
Gas project C3-054, Utah County
Gas
166 MWWithdrawn / abandoned Utah, UTWest May 2023target 2025
Solar project GEN-2022-231, Logan County
Solar
166 MWWithdrawn / abandoned Logan, OKSPP Feb 2023target 2028
ELP Clay Storage
Battery storage ยท ELP Clay Storage LLC
165 MWWithdrawn / abandoned Onondaga, NYNYISO Feb 2023
Solar project 584, Fayette County
Solar
165 MWWithdrawn / abandoned Fayette, TNSoutheast Sep 2023target 2009
Battery storage project GEN-2023-036, Jackson County
Battery storage
165 MWWithdrawn / abandoned Jackson, MOSPP Oct 2023target 2026
Lynchpin Solar
Solar + storage
165 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Other project GEN-2023-SR14, Ellis County
Other
165 MWWithdrawn / abandoned Ellis, KSSPP Feb 20232025
Solar project J2393, Coles County
Solar
164 MWWithdrawn / abandoned Coles, ILMISO Aug 2023target 2027
Solar project IC-1178, Baldwin County
Solar
160 MWWithdrawn / abandoned Baldwin, ALSoutheast Sep 2023target 2030
Elsa Hybrid
Solar + storage
160 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Solar + storage project GEN-2023-188, Cotton County
Solar + storage
160 MWWithdrawn / abandoned Cotton, OKSPP Oct 2023target 2027
Battery storage project GEN-2023-SR10, Dewey County
Battery storage
160 MWWithdrawn / abandoned Dewey, OKSPP Feb 20232025
Battery Storage
Battery storage
160 MWWithdrawn / abandoned Franklin, MAISO-NE Aug 2023target 2027
Solar + storage project G0882, Lane County
Solar + storage
160 MWWithdrawn / abandoned Lane, ORWest Jun 2023target 2030
Gibson Canyon Hybrid
Solar + storage
160 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Battery storage project C3-136, Tooele County
Battery storage
160 MWWithdrawn / abandoned Tooele, UTWest May 2023target 2027
Marble River Storage
Battery storage ยท Emeren US, LLC
160 MWWithdrawn / abandoned Clinton, NYNYISO Oct 2023
Other project G0878, Lane County
Other
160 MWWithdrawn / abandoned Lane, ORWest Jun 2023target 2030
Castle Rock Energy Storage
Battery storage
158 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2023target 2028
Grid Balance Energy Center
Battery storage
157 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Black Horse
Gas
157 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Steady Grid Energy Center
Battery storage
157 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Orchard Stand Energy Center
Battery storage
157 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Orchard Grove Energy Center
Battery storage
157 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Redpoint Hybrid
Solar + storage
157 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Battery Storage
Battery storage
156 MWWithdrawn / abandoned Fairfield, CTISO-NE Feb 2023target 2027
Cowboy Hybrid
Solar + storage
156 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Live Oak Bayou Solar SLF
Solar ยท FRESH AIR ENERGY II, LLC
156 MWWithdrawn / abandoned Matagorda, TXERCOT May 2023target 2027
Obispo Trail Energy Storage
Battery storage
156 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Callinan Solar 2
Solar + storage
156 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Kanoa Solar 2
Solar + storage
156 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Delta Oak
Battery storage
155 MWWithdrawn / abandoned CACAISO Apr 2023target 2031
Keynot Peak
Solar + storage
155 MWWithdrawn / abandoned CACAISO Apr 2023target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)