United States βΊ Grid βΊ Interconnection queues βΊ Oklahoma
SOLAR + STORAGE Β· SPPSolar + storage project GEN-2023-188, Cotton County
Solar + storage project GEN-2023-188, Cotton County is a 160 MW solar + storage request withdrawn in the SPP interconnection queue, in Cotton County, Oklahoma, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandonedAug 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2023-188
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Oklaunion - Lawton 345 kV Line
- Location
- Cotton County, Oklahoma
- Technology
- Solar: 160 MW Β· Battery
- Total requested
- 160 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 2 October 2023
- Proposed online date
- September 2027
- Withdrawn
- August 2025
Location
Marker shows the centre of Cotton County; the queue data does not give exact sites.
Other requests in Cotton County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem