United States βΊ Grid βΊ Interconnection queues βΊ Oklahoma
SOLAR Β· SPPSolar project GEN-2017-053, Cotton County
Solar project GEN-2017-053, Cotton County is a 50.0 MW solar request withdrawn in the SPP interconnection queue, in Cotton County, Oklahoma, connecting to WFEC.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2017 (completed)
- Withdrawn / abandonedDec 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2017-053
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WFEC
- Connection point (POI)
- Tap Hollister SW - PSO Walters 69 kV
- Location
- Cotton County, Oklahoma
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 4 May 2017
- Proposed online date
- January 2019
- Withdrawn
- December 2020
Location
Marker shows the centre of Cotton County; the queue data does not give exact sites.
Other requests in Cotton County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem