ONSHORE WIND Β· SPPOnshore wind project GEN-2011-035, Cotton County
Onshore wind project GEN-2011-035, Cotton County is a 20.0 MW onshore wind request withdrawn in the SPP interconnection queue, in Cotton County, Oklahoma, connecting to WFEC.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2011 (completed)
- Withdrawn / abandonedJul 2011 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2011-035
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WFEC
- Connection point (POI)
- Hollister SW- Walters 69 kV
- Location
- Cotton County, Oklahoma
- Technology
- Wind: 20.0 MW
- Total requested
- 20.0 MW
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 13 June 2011
- Proposed online date
- December 2012
- Withdrawn
- July 2011
Location
Marker shows the centre of Cotton County; the queue data does not give exact sites.
Other requests in Cotton County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem