🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in CAISO (California) — page 24

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,186619.9 GW
Active in queue188.6 GW429 requests
Agreement signed96.2 GW235 requests
Withdrawn2,186619.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,186 requests · page 24 of 44
ProjectCapacityStatusLocationRegionQueuedOnline
Rocky Hill Solar
Solar + storage
154 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2023
Alamo Springs Solar 1
Solar + storage
154 MWWithdrawn / abandoned Kern, CACAISO Apr 2015target 2023
Black Hills Playa B Solar
Solar + storage
154 MWWithdrawn / abandoned Clark, NVCAISO Apr 2019target 2023
Black Hills Playa A Solar
Solar + storage
154 MWWithdrawn / abandoned Clark, NVCAISO Apr 2019target 2023
Stargaze Solar BESS
Solar
154 MWWithdrawn / abandoned Alameda, CACAISO Apr 2018target 2021
Quartz 9
Solar
154 MWWithdrawn / abandoned Riverside, CACAISO May 2016target 2021
Limon Energy Park
Solar + storage
153 MWWithdrawn / abandoned Kern, CACAISO Apr 2018target 2020
Arroyo Reyes Solar
Solar
153 MWWithdrawn / abandoned Kings, CACAISO May 2016target 2020
Alembic
Gas
153 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
East-Bay-Wind
Onshore wind
153 MWWithdrawn / abandoned Alameda, CACAISO May 2017target 2023
Almond Wood Energy
Solar
153 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Yellow Pine 1
Solar
153 MWWithdrawn / abandoned Clark, NVCAISO May 2016target 2019
Hammock Storage
Battery storage
153 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2020target 2023
Golden Rectangle
Solar + storage
153 MWWithdrawn / abandoned Fresno, CACAISO May 2016target 2021
Halifax
Solar + storage
153 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2021target 2024
Spartan Energy Storage
Battery storage
152 MWWithdrawn / abandoned Sutter, CACAISO Apr 2020target 2023
King Flat Wind Farm 1
Onshore wind
152 MWWithdrawn / abandoned Yolo, CACAISO May 2017target 2020
Emperor Storage
Battery storage
152 MWWithdrawn / abandoned Santa Clara, CACAISO Apr 2021target 2024
Ferry Hybrid Solar
Solar + storage
152 MWWithdrawn / abandoned Madera, CACAISO Apr 2020target 2023
Mesut Storage
Battery storage
152 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Jasper Energy Storage
Battery storage
152 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Hensley Hybrid Solar
Solar + storage
152 MWWithdrawn / abandoned Madera, CACAISO Apr 2020target 2023
Rosebowl
Battery storage
152 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2024
Trivor Energy Storage
Battery storage
151 MWWithdrawn / abandoned Merced, CACAISO Apr 2021target 2025
Cazadores Storage
Battery storage
151 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2021target 2032
Avenida Del Sul
Solar
151 MWWithdrawn / abandoned Inyo, CACAISO Apr 2023target 2029
Ridge Solar Storage
Solar
151 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Falcon Energy Center
Battery storage
151 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2018target 2021
Stomper Storage
Battery storage
151 MWWithdrawn / abandoned Alameda, CACAISO Apr 2021target 2024
Ruby Energy Storage
Battery storage
151 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2021target 2024
Quail Lake Storage
Battery storage
151 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2021target 2025
Railyard Energy Storage
Battery storage
151 MWWithdrawn / abandoned Santa Clara, CACAISO Apr 2020target 2023
Alta 1 Storage
Battery storage
151 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2024
Amberjill Energy
Solar + storage
151 MWWithdrawn / abandoned Imperial, CACAISO Apr 2023target 2029
Pinscher Energy Storage
Battery storage
151 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2029
Mojave Soleil
Solar
150 MWWithdrawn / abandoned Kern, CACAISO Feb 2007target 2013
Alta 14
Solar
150 MWWithdrawn / abandoned Kern, CACAISO Jul 2010target 2014
Tulare Solar
Solar
150 MWWithdrawn / abandoned Tulare, CACAISO Mar 2011target 2014
Candlewood Wind
Onshore wind
150 MWWithdrawn / abandoned Imperial, CACAISO Mar 2011target 2013
Rancho Wistaria Solar Energy Center
Solar
150 MWWithdrawn / abandoned Imperial, CACAISO Apr 2013target 2016
Mule Mountain - C5
Solar
150 MWWithdrawn / abandoned Riverside, CACAISO Apr 2012target 2016
Antelope Valley Renewable Energy Farm - Solar
Solar
150 MWWithdrawn / abandoned Los Angeles, CACAISO Feb 2010target 2013
Firehawk Solar 1
Solar + storage
150 MWWithdrawn / abandoned Kern, CACAISO May 2017target 2020
Acorn Greenworks
Solar
150 MWWithdrawn / abandoned Imperial, CACAISO Mar 2011target 2021
Silver State South 3 Solar
Solar
150 MWWithdrawn / abandoned Clark, NVCAISO Apr 2013target 2016
Upc Grand View Winds
Onshore wind
150 MWWithdrawn / abandoned San Bernardino, CACAISO Jul 2006target 2008
Troy Lake Wind
Onshore wind
150 MWWithdrawn / abandoned San Bernardino, CACAISO Dec 2007target 2011
Maricopa California Solar Farms II
Solar
150 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2013
Green Borders Geothermal Phase 2
Geothermal
150 MWWithdrawn / abandoned Mineral, NVCAISO Mar 2007target 2011
Rice Solar Energy
Solar
150 MWWithdrawn / abandoned Riverside, CACAISO May 2008target 2014
Page 24 of 44

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)