🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Hensley Hybrid Solar

Hensley Hybrid Solar is a 152 MW solar + storage request withdrawn in the CAISO interconnection queue, in Madera County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandonedJul 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1719
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Chowchilla-Kerckhoff #2 115kV lin3
Location
Madera County, California
Technology
Solar: 102 MW · Battery: 50.0 MW
Total requested
152 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
15 April 2020
Proposed online date
November 2023
Withdrawn
July 2020

Location

Marker shows the centre of Madera County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Madera County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem