🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Golden Rectangle

Golden Rectangle is a 153 MW solar + storage request withdrawn in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedMay 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1230
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Tranquility Kearny 230kV
Location
Fresno County, California
Technology
Solar: 122 MW · Battery: 30.9 MW
Total requested
153 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
2 May 2016
Proposed online date
December 2021
Withdrawn
May 2017

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Fresno County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem