Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 231 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2216, Vigo County
Solar
100 MWWithdrawn / abandoned Vigo, INMISO Apr 2022target 2024
Solar + storage project IA-PNM-2023-31, Mckinley County
Solar + storage
100 MWWithdrawn / abandoned Mckinley, NMWest Sep 2023target 2028
GNA Energy
Gas · GNA Energy, LLC
100 MWWithdrawn / abandoned Klickitat, WAWest Aug 2001target 2003
Other project PP00032, Wake County
Other
100 MWWithdrawn / abandoned Wake, NCSoutheast Jun 2025target 2028
Solar project AH1-163
Solar · Derby Solar Farm, LLC
100 MWWithdrawn / abandoned KYPJM Sep 2021target 2025
Battery storage project J2223, Jackson County
Battery storage
100 MWWithdrawn / abandoned Jackson, ARMISO Dec 2021target 2024
Orchard BESS
Battery storage · Empire Reserve Energy, LLC
100 MWWithdrawn / abandoned Ulster, NYNYISO Aug 2024
Battery storage project 151, Pierce County
Battery storage
100 MWWithdrawn / abandoned Pierce, WAWest Apr 2024target 2027
Solar + storage project GEN-2021-087, Seward County
Solar + storage
100 MWWithdrawn / abandoned Seward, KSSPP Apr 2021target 2028
Solar project 187, Hampton County
Solar
100 MWWithdrawn / abandoned Hampton, SCSoutheast Jun 2023target 2024
Onshore wind project 54, Sweet Grass County
Onshore wind
100 MWWithdrawn / abandoned Sweet Grass, MTWest Feb 2007target 2008
Onshore wind project 41, Jefferson County
Onshore wind
100 MWWithdrawn / abandoned Jefferson, MTWest Nov 2005
Onshore wind project J978, Montcalm County
Onshore wind
100 MWWithdrawn / abandoned Montcalm, MIMISO Mar 2018target 2021
Clermont 1
Battery storage · Hecate Grid Clermont 1 LLC
100 MWWithdrawn / abandoned Suffolk, NYNYISO Oct 2019
Battery storage project AH1-063, Washington County
Battery storage
100 MWWithdrawn / abandoned Washington, VAPJM Jul 2021target 2024
Solar + storage project 140, Horry County
Solar + storage
100 MWWithdrawn / abandoned Horry, SCSoutheast May 2020target 2022
Solar project 177, Georgetown County
Solar
100 MWWithdrawn / abandoned Georgetown, SCSoutheast Feb 2022
Solar project AE2-157, Sussex County
Solar
100 MWWithdrawn / abandoned Sussex, VAPJM Mar 2019target 2021
Solar project GEN-2016-156, Texas County
Solar
100 MWWithdrawn / abandoned Texas, OKSPP Nov 2016target 2020
100MW Longview 2
Gas
100 MWWithdrawn / abandoned Cowlitz, WAWest Apr 2001target 2001
Onshore wind project J1896, Henderson County
Onshore wind
100 MWWithdrawn / abandoned Henderson, KYMISO Aug 2021target 2025
Dix Hills Storage, LLC
Battery storage · Dix Hills Storage, LLC
100 MWWithdrawn / abandoned Suffolk, NYNYISO Aug 2024
Solar project IC-340, Monroe County
Solar
100 MWWithdrawn / abandoned Monroe, GASoutheast Mar 2014
Solar project G0629, Benton County
Solar
100 MWWithdrawn / abandoned Benton, WAWest Sep 2019target 2024
Onshore wind project G513, Oceana County
Onshore wind
100 MWWithdrawn / abandoned Oceana, MIMISO Apr 2005target 2006
Battery storage project AF2-071, Mercer County
Battery storage
100 MWWithdrawn / abandoned Mercer, NJPJM Jan 2020target 2023
Other project J2196, Montgomery County
Other
100 MWWithdrawn / abandoned Montgomery, ILMISO Aug 2021target 2028
Solar + storage project GEN-2023-002, Butler County
Solar + storage
100 MWWithdrawn / abandoned Butler, KSSPP Jun 2023target 2026
Onshore wind project R48, Cherokee County
Onshore wind
100 MWWithdrawn / abandoned Cherokee, IAMISO Jan 2008target 2009
Solar project AD2-146, Butler County
Solar
100 MWWithdrawn / abandoned Butler, OHPJM Mar 2018target 2020
Wind + storage project C2-151, Linn County
Wind + storage
100 MWWithdrawn / abandoned Linn, ORWest May 2022target 2025
Solar project 20171018003, Fairfield County
Solar
100 MWWithdrawn / abandoned Fairfield, SCSoutheast target 2019
Onshore wind project GEN-2008-036, Canadian County
Onshore wind
100 MWWithdrawn / abandoned Canadian, OKSPP May 2008target 2011
Onshore wind project H017, Cottonwood County
Onshore wind
100 MWWithdrawn / abandoned Cottonwood, MNMISO Apr 2008target 2009
Solar + storage project AG2-417, Lycoming County
Solar + storage
100 MWWithdrawn / abandoned Lycoming, PAPJM Mar 2021target 2025
Solar project J3641, Dickinson County
Solar
100 MWWithdrawn / abandoned Dickinson, MIMISO Apr 2024target 2028
Onshore wind project G0237, Sherman County
Onshore wind
100 MWWithdrawn / abandoned Sherman, ORWest Oct 2006target 2009
Deer River Wind
Onshore wind · Deer River Wind, LLC
100 MWWithdrawn / abandoned Lewis, NYNYISO Jul 2016
Solar project IC-435, Taylor County
Solar
100 MWWithdrawn / abandoned Taylor, GASoutheast Feb 2016
Solar + storage project C4-047, Millard County
Solar + storage
100 MWWithdrawn / abandoned Millard, UTWest May 2024target 2027
Battery storage project J1468, Dakota County
Battery storage
100 MWWithdrawn / abandoned Dakota, MNMISO Apr 2019target 2022
Solar + storage project AG2-093, Prince George County
Solar + storage · Admiral Solar LLC
100 MWWithdrawn / abandoned Prince George, VAPJM Feb 2025target 2024
Zenobe Rotterdam LLC (NYISO-C24-191)
Battery storage
100 MWWithdrawn / abandoned Schenectady, NYISO-NE Dec 2024target 2028
Battery storage project 134, Thurston County
Battery storage
100 MWWithdrawn / abandoned Thurston, WAWest Aug 2022target 2025
Onshore wind project GEN-2007-011N03, Holt County
Onshore wind
100 MWWithdrawn / abandoned Holt, NESPP Mar 2007
Onshore wind project GEN-2015-098, Wibaux County
Onshore wind
100 MWWithdrawn / abandoned Wibaux, MTSPP Oct 2015target 2017
Solar + storage project Company 171, Clark County
Solar + storage
100 MWWithdrawn / abandoned Clark, NVWest Sep 2018target 2021
Solar project J3406, Calcasieu Parish County
Solar
100 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Apr 2024target 2028
Sandy Hills Solar
Solar · SunPower
100 MWWithdrawn / abandoned ERCOT Mar 2011target 2017
Coal project GI-0607, Beadle County
Coal
100 MWWithdrawn / abandoned Beadle, SDWest Jun 2006
Page 231 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)