United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

ONSHORE WIND Β· MISO

Onshore wind project J1896, Henderson County

Onshore wind project J1896, Henderson County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Henderson County, Kentucky, connecting to BIG RIVERS ELECTRIC CORPORATION.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedDec 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1896
Grid region
MISO (Midcontinent)
Utility / transmission owner
BIG RIVERS ELECTRIC CORPORATION
Connection point (POI)
Henderson to AB Brown 138 kV
Location
Henderson County, Kentucky
Technology
Wind: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2
Queue status
Withdrawn
Entered queue
17 August 2021
Proposed online date
April 2025
Withdrawn
December 2022

Location

Marker shows the centre of Henderson County; the queue data does not give exact sites.

Power plants in Kentucky Β· Transmission lines in Kentucky

Other requests in Henderson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem