United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2020 requests) โ€” page 22

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,752246.2 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,752 requests ยท page 22 of 36
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J1749, West Baton Rouge Parish, La County
Solar + storage
50.0 MWWithdrawn / abandoned West Baton Rouge Parish, La, LAMISO Jun 2020target 2022
Nuclear project AF2-315, Luzerne County
Nuclear
50.0 MWWithdrawn / abandoned Luzerne, PAPJM Mar 2020target 2020
Battery storage project 1RSC-2020-03, Pueblo County
Battery storage
50.0 MWWithdrawn / abandoned Pueblo, COWest Jan 2020target 2022
Mountain Trail Solar
Solar
50.0 MWWithdrawn / abandoned Berks, PAPJM Sep 2020target 2028
West Babylon Power Station Battery Energy Storage System
Battery storage ยท National Grid Generation LLC
50.0 MWWithdrawn / abandoned Suffolk, NYNYISO Jan 2020
Solar + storage project GEN-2020-030, Sarpy County
Solar + storage
50.0 MWWithdrawn / abandoned Sarpy, NESPP Apr 20202024
Solar + storage project GEN-2020-027, Sarpy County
Solar + storage
50.0 MWWithdrawn / abandoned Sarpy, NESPP Apr 20202024
Battery storage project J1535, Knox County
Battery storage
50.0 MWWithdrawn / abandoned Knox, INMISO Jun 2020target 2023
Nuclear project AF2-251, Luzerne County
Nuclear
50.0 MWWithdrawn / abandoned Luzerne, PAPJM Mar 2020target 2020
Solar project LGE-GIS-2020-001, Madison County
Solar
50.0 MWWithdrawn / abandoned Madison, KYSoutheast Oct 2020target 2024
Battery storage project AG1-454, Noble County
Battery storage ยท RWE Solar Development, LLC
50.0 MWWithdrawn / abandoned Noble, INPJM Sep 2020target 2022
Solar project AG1-418, Whitley County
Solar
50.0 MWWithdrawn / abandoned Whitley, INPJM Sep 2020target 2023
Battery storage project J1733, Allamakee County
Battery storage
50.0 MWWithdrawn / abandoned Allamakee, IAMISO Jun 2020target 2025
Solar project AG2-006, Licking County
Solar
50.0 MWWithdrawn / abandoned Licking, OHPJM Oct 2020target 2023
Solar project AF2-332, Montour County
Solar
50.0 MWWithdrawn / abandoned Montour, PAPJM Mar 2020target 2023
Solar project G0646, Union County
Solar
50.0 MWWithdrawn / abandoned Union, ORWest Apr 2020target 2023
Battery storage project J1704, Shelby County
Battery storage
50.0 MWWithdrawn / abandoned Shelby, INMISO Jun 2020target 2023
Kce NY 27
Battery storage ยท KCE NY 27, LLC
50.0 MWWithdrawn / abandoned Suffolk, NYNYISO Jun 2020
Solar project J1643, Genesee County
Solar
50.0 MWWithdrawn / abandoned Genesee, MIMISO Jun 2020target 2023
Solar + storage project IA-PNM-2020-18, Bernalillo County
Solar + storage
49.9 MWWithdrawn / abandoned Bernalillo, NMWest Oct 2020target 2022
Solar project AG1-068, Adams County
Solar
49.9 MWWithdrawn / abandoned Adams, OHPJM Jul 2020target 2023
Kent County - NG WRI DG Area Study #2 >5 MW
Solar
49.8 MWWithdrawn / abandoned Kent, RIISO-NE Aug 2020target 2025
Solar project AF2-123, Madison County
Solar
49.0 MWWithdrawn / abandoned Madison, OHPJM Feb 2020target 2023
Battery storage project AG1-185, Charlotte County
Battery storage ยท Drakes Branch Solar, LLC
48.9 MWWithdrawn / abandoned Charlotte, VAPJM Sep 2020target 2023
Barney Davis IPAC #4 repower
Gas
48.0 MWWithdrawn / abandoned Nueces, TXERCOT Jun 2020
Eversource Group @ Wareham 714
Solar + storage
48.0 MWWithdrawn / abandoned Plymouth, MAISO-NE Apr 2020target 2023
Other project AF2-320, St. Joseph County
Other
48.0 MWWithdrawn / abandoned St. Joseph, INPJM Mar 2020target 2023
Solar project 126022, York County
Solar
47.0 MWWithdrawn / abandoned York, SCSoutheast Mar 2020
Solar project AG1-428, Brunswick County
Solar ยท ACE Development Company II, LLC
46.8 MWWithdrawn / abandoned Brunswick, VAPJM Sep 2020target 2024
Solar project AG1-313, Northampton County
Solar
46.0 MWWithdrawn / abandoned Northampton, NCPJM Sep 2020target 2023
Moss Ridge Solar
Solar ยท Moss Ridge Solar 1
46.0 MWWithdrawn / abandoned St. Lawrence, NYNYISO Aug 2020
Solar project AF2-262, Luzerne County
Solar
45.0 MWWithdrawn / abandoned Luzerne, PAPJM Mar 2020target 2023
Wood Duck 100 MW
Solar ยท Wood Duck Solar LLC
45.0 MWWithdrawn / abandoned Barren, KYPJM Jul 2020target 2024
Solar project AF2-186, Paulding County
Solar
45.0 MWWithdrawn / abandoned Paulding, OHPJM Mar 2020target 2023
Solar + storage project AF2-055, Northampton County
Solar + storage
45.0 MWWithdrawn / abandoned Northampton, VAPJM Jan 2020target 2025
Kce NY 28
Battery storage ยท KCE NY 28, LLC
45.0 MWWithdrawn / abandoned Suffolk, NYNYISO Aug 2020
Eversource Group @ West Pond 737
Solar + storage
44.1 MWWithdrawn / abandoned Plymouth, MAISO-NE Apr 2020target 2023
Solar project J1636, Pike County
Solar
44.0 MWWithdrawn / abandoned Pike, MOMISO Jun 2020target 2023
Solar project AF2-323, Crawford County
Solar
44.0 MWWithdrawn / abandoned Crawford, PAPJM Mar 2020target 2022
Victory Solar
Solar
44.0 MWWithdrawn / abandoned Crawford, PAPJM Sep 2020target 2026
Solar project J1569, Pierce County
Solar
44.0 MWWithdrawn / abandoned Pierce, WIMISO Jun 2020target 2023
Onshore wind project J1729, Hancock County
Onshore wind
43.0 MWWithdrawn / abandoned Hancock, IAMISO Jun 2020target 2023
Solar project J1699, Shelby County
Solar
43.0 MWWithdrawn / abandoned Shelby, INMISO Jun 2020target 2024
Battery storage project AF2-329, Kendall County
Battery storage ยท Plano Skies Energy Center, LLC
42.2 MWWithdrawn / abandoned Kendall, ILPJM Mar 2020target 2023
Onshore wind project J1758, Barnes County
Onshore wind
42.0 MWWithdrawn / abandoned Barnes, NDMISO Jun 2020target 2023
Solar project AF2-084, Union County
Solar
42.0 MWWithdrawn / abandoned Union, OHPJM Jan 2020target 2022
Solar project AG2-064, Caroline County
Solar
41.0 MWWithdrawn / abandoned Caroline, VAPJM Dec 2020target 2023
Mariposa Energy BESS
Gas
40.3 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2020target 2027
Battery storage project J1517, Vermillion County
Battery storage
40.0 MWWithdrawn / abandoned Vermillion, INMISO Jun 2020target 2023
University Park North Energy Center
Battery storage
40.0 MWWithdrawn / abandoned Will, ILPJM Sep 2020target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)