United States βΊ Grid βΊ Interconnection queues βΊ Missouri
SOLAR Β· MISOSolar project J1636, Pike County
Solar project J1636, Pike County is a 44.0 MW solar request withdrawn in the MISO interconnection queue, in Pike County, Missouri, connecting to AMEREN MISSOURI.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandonedSep 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1636
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN MISSOURI
- Connection point (POI)
- Peno Creek Substation 161kV
- Location
- Pike County, Missouri
- Technology
- Solar: 44.0 MW
- Total requested
- 44.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 23 June 2020
- Proposed online date
- September 2023
- Withdrawn
- September 2024
Location
Marker shows the centre of Pike County; the queue data does not give exact sites.
Other requests in Pike County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem