πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

GAS Β· ERCOT

Barney Davis IPAC #4 repower

Barney Davis IPAC #4 repower is a 48.0 MW gas request withdrawn in the ERCOT interconnection queue, in Nueces County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2020 (completed)
  2. Withdrawn / abandonedJul 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
20INR0312
Grid region
ERCOT (Texas)
Location
Nueces County, Texas
Technology
Gas: 48.0 MW
Total requested
48.0 MW
Queue status
Withdrawn
Entered queue
18 June 2020
Withdrawn
July 2021

Location

Marker shows the centre of Nueces County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Nueces County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem