United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Oklahoma (2025 requests) β€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9527.4 GW
Active in queue27.4 GW95 requests
Agreement signed0.0 MW0 requests
Withdrawn309,677 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

95 requests Β· page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project GEN-2024-120, Oklahoma County
Battery storage
199 MWIn study Oklahoma, OKSPP Mar 2025target 2028
Battery storage project GEN-2024-164, Murray County
Battery storage
199 MWIn study Murray, OKSPP Mar 2025target 2030
Battery storage project GEN-2024-187, Mcclain County
Battery storage
199 MWIn study Mcclain, OKSPP Mar 2025target 2029
Wind + storage project GEN-2024-308, Woodward County
Wind + storage
199 MWIn study Woodward, OKSPP Mar 2025target 2030
Battery storage project GEN-2024-250, Pittsburg County
Battery storage
199 MWIn study Pittsburg, OKSPP Mar 2025target 2029
Battery storage project GEN-2024-184, Atoka County
Battery storage
199 MWIn study Atoka, OKSPP Mar 2025target 2029
Battery storage project GEN-2024-318, Tulsa County
Battery storage
199 MWIn study Tulsa, OKSPP Mar 2025target 2028
Battery storage project GEN-2024-119, Cleveland County
Battery storage
199 MWIn study Cleveland, OKSPP Mar 2025target 2028
Battery storage project GEN-2024-245, Lincoln County
Battery storage
199 MWIn study Lincoln, OKSPP Mar 2025target 2029
Battery storage project GEN-2024-118, Wagoner County
Battery storage
199 MWIn study Wagoner, OKSPP Mar 2025target 2028
Solar + storage project GEN-2024-267, Bryan County
Solar + storage
195 MWIn study Bryan, OKSPP Mar 2025target 2029
Solar project GEN-2024-158, Jackson County
Solar
190 MWIn study Jackson, OKSPP Mar 2025target 2029
Gas project ERAS-2025-003, Oklahoma County
Gas
186 MWIn study Oklahoma, OKSPP Sep 20252025
Battery storage project GEN-2025-SR14, Oklahoma County
Battery storage
183 MWIn study Oklahoma, OKSPP May 2025target 2030
Solar project ERAS-2025-025, Caddo County
Solar
175 MWIn study Caddo, OKSPP Oct 2025target 2027
Solar + storage project GEN-2024-161, Jackson County
Solar + storage
170 MWIn study Jackson, OKSPP Mar 2025target 2030
Solar project GEN-2024-297, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Solar project GEN-2024-296, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Solar project GEN-2024-298, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Solar + storage project GEN-2024-219, Murray County
Solar + storage
160 MWIn study Murray, OKSPP Mar 2025target 2030
Solar + storage project GEN-2024-360, Seminole County
Solar + storage
160 MWIn study Seminole, OKSPP Mar 2025target 2029
Battery storage project GEN-2024-244, Texas County
Battery storage
150 MWIn study Texas, OKSPP Mar 2025target 2029
Battery storage project GEN-2024-332, Oklahoma County
Battery storage
150 MWIn study Oklahoma, OKSPP Mar 2025target 2027
Solar + storage project GEN-2024-117, Washington County
Solar + storage
150 MWIn study Washington, OKSPP Mar 2025target 2028
Solar + storage project GEN-2024-362, Grady County
Solar + storage
140 MWIn study Grady, OKSPP Mar 2025target 2029
Solar project GEN-2024-157, Kiowa County
Solar
140 MWIn study Kiowa, OKSPP Mar 2025target 2029
Gas project GEN-2024-286, Le Flore County
Gas
136 MWIn study Le Flore, OKSPP Mar 2025target 2031
Other project GEN-2025-SR13, Seminole County
Other
130 MWIn study Seminole, OKSPP May 2025target 2029
Other project GEN-2025-SR15, Mcclain County
Other
125 MWIn study Mcclain, OKSPP May 2025target 2029
Gas project GEN-2024-334, Kay County
Gas
124 MWIn study Kay, OKSPP Mar 2025target 2029
Battery storage project ERAS-2025-022, Pontotoc County
Battery storage
123 MWIn study Pontotoc, OKSPP Oct 2025target 2028
Solar + storage project GEN-2024-373, Choctaw County
Solar + storage
120 MWIn study Choctaw, OKSPP Mar 2025target 2029
Battery storage project GEN-2025-SR12, Noble County
Battery storage
116 MWIn study Noble, OKSPP May 2025target 2030
Battery storage project GEN-2025-SR11, Noble County
Battery storage
112 MWIn study Noble, OKSPP May 2025target 2030
Battery storage project GEN-2025-SR7, Muskogee County
Battery storage
102 MWIn study Muskogee, OKSPP May 2025target 2026
Battery storage project GEN-2024-333, Oklahoma County
Battery storage
100 MWIn study Oklahoma, OKSPP Mar 2025target 2027
Other project GEN-2025-SR19, Chouteau County
Other
100 MWIn study Chouteau, OKSPP Jun 2025target 2029
Other project GEN-2025-SR23, Oklahoma County
Other
100 MWIn study Oklahoma, OKSPP Jun 2025target 2026
Other project GEN-2025-SR21, Tulsa County
Other
100 MWIn study Tulsa, OKSPP Jun 2025target 2028
Battery storage project GEN-2024-180, Mayes County
Battery storage
100 MWIn study Mayes, OKSPP Mar 2025target 2029
Other project GEN-2025-SR22, Oklahoma County
Other
100 MWIn study Oklahoma, OKSPP Jun 2025target 2028
Battery storage project GEN-2024-204, Bryan County
Battery storage
100 MWIn study Bryan, OKSPP Mar 2025target 2030
Solar + storage project GEN-2024-361, Lincoln County
Solar + storage
80.0 MWIn study Lincoln, OKSPP Mar 2025target 2029
Onshore wind project GEN-2026-PR3, Garfield County
Onshore wind
49.7 MWIn study Garfield, OKSPP Dec 2025target 2030
Onshore wind project GEN-2026-PR2, Dewey County
Onshore wind
41.9 MWIn study Dewey, OKSPP Dec 2025target 2030
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)