United States โ€บ Grid โ€บ Interconnection queues โ€บ New York

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in New York (2024 requests) โ€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8614.6 GW
Active in queue14.6 GW86 requests
Agreement signed0.0 MW0 requests
Withdrawn28761.7 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

86 requests ยท page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Coral Energy Storage
Battery storage ยท Hanwha Q CELLS USA Corp.
100 MWIn study Chemung, NYNYISO Aug 2024target 2027
Mill Point Solar II
Solar + storage ยท ConnectGen Montgomery County LLC
100 MWIn study Montgomery, NYNYISO Oct 2024target 2028
South Bronx Energy Storage
Battery storage ยท Prologis Energy LLC
100 MWIn study Bronx, NYNYISO Sep 2024target 2030
Marlboro Storage
Battery storage ยท Origis Development LLC
100 MWIn study Ulster, NYNYISO Oct 2024target 2028
Eastwater Energy Storage
Battery storage ยท GCI Eastwater, LLC
100 MWIn study Monroe, NYNYISO Aug 2024target 2027
Horseblock Energy Storage
Battery storage ยท ACE DevCo NC, LLC
100 MWIn study Suffolk, NYNYISO Aug 2024target 2028
Zenobe Burns LLC
Battery storage ยท Zenobe Americas Inc.
100 MWIn study Allegany, NYNYISO Sep 2024target 2028
Alcazar 1
Battery storage ยท Terra-Gen Development Company, LLC
100 MWIn study Ulster, NYNYISO Aug 2024target 2028
Fort Edward Solar Farm (NY53)
Solar ยท Fort Edward Solar LLC
100 MWIn study Washington, NYNYISO Aug 2024target 2027
Arch 3
Battery storage ยท Terra-Gen Development Company, LLC
100 MWIn study Orange, NYNYISO Aug 2024target 2028
Kce NY 34
Battery storage ยท KCE NY 34, LLC
100 MWIn study Ulster, NYNYISO Sep 2024target 2029
Jericho Solar
Solar ยท Jericho Solar Park LLC
100 MWIn study Franklin, NYNYISO Oct 2024target 2029
Aria Storage 1
Battery storage ยท Terra-Gen Development Company, LLC
100 MWIn study Dutchess, NYNYISO Oct 2024target 2028
Hemlock Hollow Wind
Onshore wind ยท Liberty Renewables Inc.
95.0 MWIn study Cattaraugus, NYNYISO Aug 2024target 2029
Hell Gate Energy Storage
Battery storage ยท the NY Power Authority
90.0 MWIn study Bronx, NYNYISO Oct 2024target 2028
Bassett Energy Storage
Battery storage ยท Bassett Energy Storage
79.9 MWIn study Steuben, NYNYISO Sep 2024target 2028
Daphne Energy Storage
Battery storage ยท Hanwha Q CELLS USA Corp.
75.0 MWIn study Suffolk, NYNYISO Aug 2024target 2027
Leo Energy Storage
Battery storage ยท BGTF US Development Holdings LLC
75.0 MWIn study Clinton, NYNYISO Oct 2024target 2028
Dewdrop Wind
Onshore wind ยท Dewdrop Wind LLC
62.0 MWIn study Chautauqua, NYNYISO Sep 2024target 2029
Cayuga Solar
Solar ยท Cayuga Lake Solar, LLC
60.0 MWIn study Tompkins, NYNYISO Sep 2024target 2028
Kce NY 21
Battery storage ยท KCE NY 21, LLC
60.0 MWIn study Suffolk, NYNYISO Aug 2024target 2029
Town Line Solar Phase II
Solar + storage ยท RWE Solar Development, LLC
60.0 MWIn study Sullivan, NYNYISO Sep 2024target 2030
Sandlot IFB
Battery storage ยท Sandlot Energy LLC
50.0 MWIn study Suffolk, NYNYISO Sep 2024target 2028
Azalea Wind 1
Onshore wind ยท Azalea Wind LLC
50.0 MWIn study Schuyler, NYNYISO Oct 2024target 2029
Azalea Wind 2
Onshore wind ยท Azalea Wind LLC
50.0 MWIn study Schuyler, NYNYISO Oct 2024target 2029
Kce NY 31
Battery storage ยท KCE NY 31, LLC
50.0 MWIn study Suffolk, NYNYISO Aug 2024target 2027
Porter Energy Storage
Battery storage ยท BGTF US Development Holdings LLC
50.0 MWIn study Essex, NYNYISO Sep 2024target 2028
Kce NY 30
Battery storage ยท KCE NY 30, LLC
50.0 MWIn study Suffolk, NYNYISO Aug 2024target 2028
Buttercup Wind
Onshore wind ยท Buttercup Wind LLC
49.9 MWIn study Chautauqua, NYNYISO Sep 2024target 2029
Brentwood Energy Storage
Battery storage ยท the NY Power Authority
49.1 MWIn study Suffolk, NYNYISO Sep 2024target 2028
Pouch Energy Storage System
Battery storage ยท the NY Power Authority
47.1 MWIn study Kings, NYNYISO Oct 2024target 2028
Troy Heights Energy Storage
Battery storage ยท Nexamp Solar LLC
40.0 MWIn study Tompkins, NYNYISO Sep 2024target 2028
Sherburne Storage
Battery storage ยท Nexamp Solar LLC
40.0 MWIn study Chenango, NYNYISO Oct 2024target 2028
Goldenrod Wind
Onshore wind ยท Goldenrod Wind LLC
39.0 MWIn study Chautauqua, NYNYISO Sep 2024target 2029
Hoffman Falls Wind 2
Onshore wind ยท Liberty Renewables Inc.
29.8 MWIn study Madison, NYNYISO Aug 2024target 2027
Oswego Clean Energy
Solar ยท Oswego Clean Energy Holdings
24.9 MWIn study Oswego, NYNYISO Sep 2024target 2026
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)