🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Nebraska

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Nebraska — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown25545.7 GW
Active in queue16.5 GW85 requests
Agreement signed5,103 MW29 requests
Withdrawn25545.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

255 requests · page 2 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2024-150, Cheyenne County
Onshore wind
294 MWWithdrawn / abandoned Cheyenne, NESPP Mar 2025target 2030
Onshore wind project GEN-2022-188, Banner County
Onshore wind
290 MWWithdrawn / abandoned Banner, NESPP Feb 2023target 2026
Onshore wind project GEN-2017-165, Holt County
Onshore wind
288 MWWithdrawn / abandoned Holt, NESPP Nov 2017target 2020
Onshore wind project GEN-2022-050, Dawson County
Onshore wind
272 MWWithdrawn / abandoned Dawson, NESPP Jun 20222025
Solar project GEN-2022-077, Chase County
Solar
255 MWWithdrawn / abandoned Chase, NESPP Sep 2022target 2026
Onshore wind project GEN-2017-138, Holt County
Onshore wind
252 MWWithdrawn / abandoned Holt, NESPP Nov 2017target 2020
Onshore wind project GEN-2017-139, Holt County
Onshore wind
252 MWWithdrawn / abandoned Holt, NESPP Nov 2017target 2020
Onshore wind project GEN-2024-152, Cheyenne County
Onshore wind
250 MWWithdrawn / abandoned Cheyenne, NESPP Mar 2025target 2030
Onshore wind project GEN-2023-133, Custer County
Onshore wind
250 MWWithdrawn / abandoned Custer, NESPP Oct 2023target 2030
Coal project GEN-2001-029N1, Adams County
Coal
250 MWWithdrawn / abandoned Adams, NESPP Sep 2001
Onshore wind project GEN-2018-083, Madison County
Onshore wind
250 MWWithdrawn / abandoned Madison, NESPP Nov 2018target 2027
Onshore wind project GEN-2013-024, Cherry County
Onshore wind
250 MWWithdrawn / abandoned Cherry, NESPP Sep 2013target 2018
Onshore wind project GEN-2017-001, Custer County
Onshore wind
250 MWWithdrawn / abandoned Custer, NESPP Dec 2016target 2023
Solar project GEN-2020-051, Lincoln County
Solar
250 MWWithdrawn / abandoned Lincoln, NESPP Apr 20202025
Solar project GEN-2020-004, Otoe County
Solar
250 MWWithdrawn / abandoned Otoe, NESPP Apr 2020target 2026
Onshore wind project GEN-2006-038N009, Knox County
Onshore wind
250 MWWithdrawn / abandoned Knox, NESPP Oct 2006
Gas project GEN-2008-121O, Cass County
Gas
249 MWWithdrawn / abandoned Cass, NESPP Oct 2008target 2014
Onshore wind project GEN-2021-037, Perkins County
Onshore wind
244 MWWithdrawn / abandoned Perkins, NESPP May 2021target 2026
Solar + storage project GEN-2022-210, Lancaster County
Solar + storage
240 MWWithdrawn / abandoned Lancaster, NESPP Mar 2023target 2027
Solar project GEN-2021-073, Lancaster County
Solar
240 MWWithdrawn / abandoned Lancaster, NESPP May 2021target 2027
Onshore wind project GEN-2013-021, Keith County
Onshore wind
230 MWWithdrawn / abandoned Keith, NESPP Jul 2013target 2016
Solar project GEN-2017-055, Lancaster County
Solar
228 MWWithdrawn / abandoned Lancaster, NESPP May 20172023
Onshore wind project GEN-2016-096, Fillmore County
Onshore wind
228 MWWithdrawn / abandoned Fillmore, NESPP Nov 20162020
Solar + storage project GEN-2022-212, Lancaster County
Solar + storage
225 MWWithdrawn / abandoned Lancaster, NESPP Mar 2023target 2027
Coal project GEN-2004-018N, Adams County
Coal
220 MWWithdrawn / abandoned Adams, NESPP Sep 2004target 2011
Battery storage project GEN-2022-SR7, Franklin County
Battery storage
210 MWWithdrawn / abandoned Franklin, NESPP Jul 20222018
Solar project GEN-2022-SR8, Franklin County
Solar
210 MWWithdrawn / abandoned Franklin, NESPP Jul 2022
Onshore wind project GI-0816, Scotts Bluff County
Onshore wind
204 MWWithdrawn / abandoned Scotts Bluff, NEWest Jul 2008target 2010
Onshore wind project GI-0815, Cheyenne County
Onshore wind
204 MWWithdrawn / abandoned Cheyenne, NEWest Jul 2008target 2010
Onshore wind project GEN-2016-165, Knox County
Onshore wind
202 MWWithdrawn / abandoned Knox, NESPP Nov 2016target 2019
Onshore wind project GEN-2008-030N, Dixon County
Onshore wind
201 MWWithdrawn / abandoned Dixon, NESPP Apr 2008
Solar + storage project GEN-2023-083, Banner County
Solar + storage
200 MWWithdrawn / abandoned Banner, NESPP Oct 2023target 2027
Onshore wind project GEN-2023-218, Knox County
Onshore wind
200 MWWithdrawn / abandoned Knox, NESPP Oct 2023target 2026
Onshore wind project GEN-2023-216, Knox County
Onshore wind
200 MWWithdrawn / abandoned Knox, NESPP Oct 2023target 2026
Solar + storage project GEN-2023-071, Keith County
Solar + storage
200 MWWithdrawn / abandoned Keith, NESPP Oct 2023target 2027
Coal project GEN-2007-011N, Lancaster County
Coal
200 MWWithdrawn / abandoned Lancaster, NESPP Mar 2007
Onshore wind project GEN-2012-018, Dixon County
Onshore wind
200 MWWithdrawn / abandoned Dixon, NESPP Sep 2012target 2014
Onshore wind project GEN-2006-038N010, Cedar County
Onshore wind
200 MWWithdrawn / abandoned Cedar, NESPP Oct 2006
Solar project GEN-2021-105, Lancaster County
Solar
200 MWWithdrawn / abandoned Lancaster, NESPP May 2021target 2027
Onshore wind project GEN-2013-040, Butler County
Onshore wind
200 MWWithdrawn / abandoned Butler, NESPP Dec 2013target 2016
Solar project GEN-2020-001, Cheyenne County
Solar
200 MWWithdrawn / abandoned Cheyenne, NESPP Dec 2019target 2027
Onshore wind project GEN-2023-217, Knox County
Onshore wind
200 MWWithdrawn / abandoned Knox, NESPP Oct 2023target 2026
Battery storage project GEN-2023-189, Lancaster County
Battery storage
200 MWWithdrawn / abandoned Lancaster, NESPP Oct 2023target 2030
Battery storage project GEN-2018-036, Scotts Bluff County
Battery storage
200 MWWithdrawn / abandoned Scotts Bluff, NESPP May 20182023
Onshore wind project GI-2018-11, Banner County
Onshore wind
199 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-9, Banner County
Onshore wind
199 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Battery storage project GEN-2024-179, Douglas County
Battery storage
199 MWWithdrawn / abandoned Douglas, NESPP Mar 2025target 2029
Battery storage project GEN-2024-188, Douglas County
Battery storage
199 MWWithdrawn / abandoned Douglas, NESPP Mar 2025target 2029
Onshore wind project GEN-2023-011, Jefferson County
Onshore wind
190 MWWithdrawn / abandoned Jefferson, NESPP Oct 2023target 2030
Onshore wind project GEN-2022-039, Gage County
Onshore wind
185 MWWithdrawn / abandoned Gage, NESPP Jun 20222025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)