ONSHORE WIND Β· SPP

Onshore wind project GEN-2017-165, Holt County

Onshore wind project GEN-2017-165, Holt County is a 288 MW onshore wind request withdrawn in the SPP interconnection queue, in Holt County, Nebraska.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2017 (completed)
  2. Withdrawn / abandonedMar 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-165
Grid region
SPP (Southwest Power Pool)
Connection point (POI)
Grand Prairie-Grand Island (Holt County NE) 345kV
Location
Holt County, Nebraska
Technology
Wind: 288 MW
Total requested
288 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 November 2017
Proposed online date
December 2020
Withdrawn
March 2019

Location

Marker shows the centre of Holt County; the queue data does not give exact sites.

Power plants in Nebraska Β· Transmission lines in Nebraska

Other requests in Holt County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem