United States βΊ Grid βΊ Interconnection queues βΊ Nebraska
ONSHORE WIND Β· SPPOnshore wind project GEN-2023-216, Knox County
Onshore wind project GEN-2023-216, Knox County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Knox County, Nebraska, connecting to NPPD.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandonedAug 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2023-216
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- NPPD
- Connection point (POI)
- Hoskins 345 kV Substation via Turtle Creek 345 kV Substation
- Location
- Knox County, Nebraska
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 2 October 2023
- Proposed online date
- December 2026
- Withdrawn
- August 2025
Location
Marker shows the centre of Knox County; the queue data does not give exact sites.
Other requests in Knox County
- Onshore wind project GEN-2007-011N08, Knox CountyOnshore wind Β· 81.0 MW Β· built
- Onshore wind project GEN-2006-020N, Knox CountyOnshore wind Β· 42.0 MW Β· built
- Onshore wind project GEN-2021-007, Knox CountyOnshore wind Β· 600 MW Β· withdrawn
- Onshore wind project GEN-2006-038N009, Knox CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2016-165, Knox CountyOnshore wind Β· 202 MW Β· withdrawn
- Onshore wind project GEN-2023-218, Knox CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GEN-2023-217, Knox CountyOnshore wind Β· 200 MW Β· withdrawn
- Solar project GEN-2019-033, Knox CountySolar Β· 182 MW Β· withdrawn
- Onshore wind project GEN-2018-130, Knox CountyOnshore wind Β· 122 MW Β· withdrawn
- Solar project GEN-2018-056, Knox CountySolar Β· 103 MW Β· withdrawn
- Onshore wind project GEN-2012-005, Knox CountyOnshore wind Β· 81.0 MW Β· withdrawn
- Onshore wind project GEN-2014-023, Knox CountyOnshore wind Β· 79.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem