πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Nebraska

SOLAR + STORAGE Β· SPP

Solar + storage project GEN-2022-212, Lancaster County

Solar + storage project GEN-2022-212, Lancaster County is a 225 MW solar + storage request withdrawn in the SPP interconnection queue, in Lancaster County, Nebraska, connecting to NPPD.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2023 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-212
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Connection point (POI)
New GGS Satellite 345 kV Substation
Location
Lancaster County, Nebraska
Technology
Solar: 225 MW Β· Battery
Total requested
225 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
1 March 2023
Proposed online date
December 2027
Withdrawn
November 2023

Location

Marker shows the centre of Lancaster County; the queue data does not give exact sites.

Power plants in Nebraska Β· Transmission lines in Nebraska

Other requests in Lancaster County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem