United States › Grid › Interconnection queues › Indiana

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Indiana — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown579114.4 GW
Active in queue59.6 GW300 requests
Agreement signed11.2 GW69 requests
Withdrawn579114.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

579 requests · page 2 of 12
ProjectCapacityStatusLocationRegionQueuedOnline
Other project G088, Shelby County
Other
350 MWWithdrawn / abandoned Shelby, INMISO Mar 2001target 2007
Solar project J2194, Sullivan County
Solar
350 MWWithdrawn / abandoned Sullivan, INMISO Aug 2021target 2024
Paddlefish Solar
Solar + storage
350 MWWithdrawn / abandoned Wells, INPJM Sep 2019target 2029
Solar project AG1-225, Adams County
Solar · ADAMS SOLAR PROJECT, LLC
346 MWWithdrawn / abandoned Adams, INPJM Sep 2020target 2023
Other project AG2-556, Vigo County
Other
339 MWWithdrawn / abandoned Vigo, INPJM Mar 2021target 2024
Solar project AG2-219, Decatur County
Solar · Cobia Solar LLC
330 MWWithdrawn / abandoned Decatur, INPJM Feb 2025target 2024
Other project G080, Vermillion County
Other
320 MWWithdrawn / abandoned Vermillion, INMISO Feb 2001target 2004
Onshore wind project J2241, Benton County
Onshore wind
320 MWWithdrawn / abandoned Benton, INMISO Aug 2021target 2024
Solar project AE1-089, St. Joseph County
Solar
310 MWWithdrawn / abandoned St. Joseph, INPJM Aug 2018target 2021
Other project AD2-080, St. Joseph County
Other
309 MWWithdrawn / abandoned St. Joseph, INPJM Mar 2018target 2020
Solar + storage project J1756, Shelby County
Solar + storage
309 MWWithdrawn / abandoned Shelby, INMISO Jun 2020target 2023
Onshore wind project J754, Montgomery County
Onshore wind
304 MWWithdrawn / abandoned Montgomery, INMISO Nov 2016target 2020
Onshore wind project AE1-211, Jasper County
Onshore wind
302 MWWithdrawn / abandoned Jasper, INPJM Sep 2018target 2020
Onshore wind project H087, Porter County
Onshore wind
300 MWWithdrawn / abandoned Porter, INMISO Jul 2008target 2012
Solar project AG1-523, Sullivan County
Solar · PJM Solar Devco I, LLC
300 MWWithdrawn / abandoned Sullivan, INPJM Sep 2020target 2023
Battery storage project J3678, Vermillion County
Battery storage
300 MWWithdrawn / abandoned Vermillion, INMISO Apr 2024target 2027
Battery storage project AG2-690, Sullivan County
Battery storage · Solar Prairie Holdco, LLC
300 MWWithdrawn / abandoned Sullivan, INPJM Mar 2021target 2024
Solar project J2269, Fountain County
Solar
300 MWWithdrawn / abandoned Fountain, INMISO Jun 2022target 2024
Solar project AG2-454, Fountain County
Solar · ALGONQUIN POWER (FOUNTAIN COUNTY SOLAR), LLC
300 MWWithdrawn / abandoned Fountain, INPJM Mar 2021target 2024
Onshore wind project AC1-059, Fayette County
Onshore wind
300 MWWithdrawn / abandoned Fayette, INPJM Sep 2016target 2018
Wells County Wind Farm
Onshore wind
300 MWWithdrawn / abandoned Wells, INPJM Aug 2009target 2014
Blue River Storage
Battery storage · Hecate Energy Blue River LLC
300 MWWithdrawn / abandoned Shelby, INPJM Sep 2020target 2023
Battery storage project J3694, Vermillion County
Battery storage
300 MWWithdrawn / abandoned Vermillion, INMISO Apr 2024target 2026
Onshore wind project V4-021, Wells County
Onshore wind
300 MWWithdrawn / abandoned Wells, INPJM Nov 2009target 2014
Gas project G399, Vigo County
Gas
300 MWWithdrawn / abandoned Vigo, INMISO Jul 2004target 2004
Other project G122, Knox County
Other
300 MWWithdrawn / abandoned Knox, INMISO Aug 2001target 2005
Solar + storage project J3113, Greene County
Solar + storage
300 MWWithdrawn / abandoned Greene, INMISO Sep 2022target 2026
Onshore wind project AH1-289, Vermillion County
Onshore wind
300 MWWithdrawn / abandoned Vermillion, INPJM Sep 2021target 2028
Battery storage project J3424, Posey County
Battery storage
300 MWWithdrawn / abandoned Posey, INMISO Apr 2024target 2028
Solar + storage project J2687, Hancock County
Solar + storage
300 MWWithdrawn / abandoned Hancock, INMISO Sep 2022target 2026
Solar project AG1-524, Sullivan County
Solar · PJM Solar Devco I, LLC
300 MWWithdrawn / abandoned Sullivan, INPJM Sep 2020target 2023
Solar + storage project J3318, Sullivan County
Solar + storage
300 MWWithdrawn / abandoned Sullivan, INMISO Apr 2024target 2028
Onshore wind project J827, Fountain County
Onshore wind
300 MWWithdrawn / abandoned Fountain, INMISO Jun 2017target 2020
Onshore wind project J2038, Montgomery County
Onshore wind
300 MWWithdrawn / abandoned Montgomery, INMISO Aug 2021target 2024
Solar project J3499, Kosciusko County
Solar
300 MWWithdrawn / abandoned Kosciusko, INMISO Apr 2024target 2028
Other project G116, Knox County
Other
300 MWWithdrawn / abandoned Knox, INMISO Aug 2001target 2005
Solar project J3383, Boone County
Solar
300 MWWithdrawn / abandoned Boone, INMISO Apr 2024target 2028
Solar project AG1-522, Sullivan County
Solar · PJM Solar Devco I, LLC
300 MWWithdrawn / abandoned Sullivan, INPJM Sep 2020target 2023
Solar project AG2-683, Sullivan County
Solar
300 MWWithdrawn / abandoned Sullivan, INPJM Mar 2021target 2024
Onshore wind project H014, Rush County
Onshore wind
300 MWWithdrawn / abandoned Rush, INMISO Apr 2008target 2011
Solar project AG1-525, Sullivan County
Solar · PJM Solar Devco I, LLC
300 MWWithdrawn / abandoned Sullivan, INPJM Sep 2020target 2023
Battery storage project J3693, Marshall County
Battery storage
300 MWWithdrawn / abandoned Marshall, INMISO Apr 2024target 2026
Liberty II Storage
Battery storage · Liberty Madison Storage LLC
300 MWWithdrawn / abandoned Madison, INPJM Mar 2020target 2022
Solar project AG2-083, Howard County
Solar
300 MWWithdrawn / abandoned Howard, INPJM Jan 2021target 2023
Onshore wind project J2132, Vermillion County
Onshore wind
300 MWWithdrawn / abandoned Vermillion, INMISO Oct 2022target 2024
Battery storage project J3810, Knox County
Battery storage
300 MWWithdrawn / abandoned Knox, INMISO Apr 2024target 2026
Solar project J1682, Boone County
Solar
300 MWWithdrawn / abandoned Boone, INMISO Jun 2020target 2024
Onshore wind project V4-033, Randolph County
Onshore wind
299 MWWithdrawn / abandoned Randolph, INPJM Dec 2009target 2018
Solar project J1742, Porter County
Solar
294 MWWithdrawn / abandoned Porter, INMISO Jun 2020target 2023
Solar project J1700, Johnson County
Solar
288 MWWithdrawn / abandoned Johnson, INMISO Jun 2020target 2023
Page 2 of 12

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)