United States βΊ Grid βΊ Interconnection queues βΊ Indiana
ONSHORE WIND Β· MISOOnshore wind project H087, Porter County
Onshore wind project H087, Porter County is a 300 MW onshore wind request withdrawn in the MISO interconnection queue, in Porter County, Indiana.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2008 (completed)
- Withdrawn / abandonedJan 2010 (project stopped here)
- ConsentedJan 2010 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- H087
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Schafer Gen - Tower Rd 345kV
- Location
- Porter County, Indiana
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 10 July 2008
- Agreement signed
- 14 January 2010
- Proposed online date
- December 2012
- Withdrawn
- January 2010
Location
Marker shows the centre of Porter County; the queue data does not give exact sites.
Other requests in Porter County
- Solar project J1407, Porter CountySolar Β· 100 MW Β· agreement signed
- Malden CCGTGas Β· 1,090 MW Β· in study
- Malden BESSBattery storage Β· 630 MW Β· in study
- Battery storage project J3140, Porter CountyBattery storage Β· 50.0 MW Β· in study
- Solar project J1742, Porter CountySolar Β· 294 MW Β· withdrawn
- Solar project J1447, Porter CountySolar Β· 250 MW Β· withdrawn
- Solar project J1412, Porter CountySolar Β· 250 MW Β· withdrawn
- Solar project J2711, Porter CountySolar Β· 122 MW Β· withdrawn
- Solar project J1960, Porter CountySolar Β· 100 MW Β· withdrawn
- Battery storage project J1683, Porter CountyBattery storage Β· 75.0 MW Β· withdrawn
- Battery storage project J1976, Porter CountyBattery storage Β· 25.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem