United States › Grid › Interconnection queues › Illinois

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Illinois — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown670115.3 GW
Active in queue74.6 GW423 requests
Agreement signed7,430 MW51 requests
Withdrawn670115.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

670 requests · page 2 of 14
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J3509, Sangamon County
Battery storage
380 MWWithdrawn / abandoned Sangamon, ILMISO Apr 2024target 2027
Gas project V1-022, Kendall County
Gas
380 MWWithdrawn / abandoned Kendall, ILPJM Mar 2009target 2015
Solar project J2579, Tazewell County
Solar
362 MWWithdrawn / abandoned Tazewell, ILMISO Sep 2022target 2027
Gas project Y2-103, Lake County
Gas
360 MWWithdrawn / abandoned Lake, ILPJM Nov 2012target 2016
Solar + storage project AE1-198, Mchenry County
Solar + storage
357 MWWithdrawn / abandoned Mchenry, ILPJM Sep 2018target 2021
Nuclear project Y1-005, Lasalle County
Nuclear
350 MWWithdrawn / abandoned Lasalle, ILPJM Feb 2012target 2016
Solar project J3482, Mclean County
Solar
350 MWWithdrawn / abandoned Mclean, ILMISO Apr 2024target 2028
Onshore wind project T105, Livingston County
Onshore wind
350 MWWithdrawn / abandoned Livingston, ILPJM Nov 2007target 2012
Garden Prairie Energy Facility
Gas
350 MWWithdrawn / abandoned Boone, ILPJM Apr 2016target 2024
Nuclear project W1-040, Lasalle County
Nuclear
350 MWWithdrawn / abandoned Lasalle, ILPJM Feb 2010target 2016
Solar + storage project AH1-755, Livingston County
Solar + storage · Livingston County Solar, LLC
330 MWWithdrawn / abandoned Livingston, ILPJM target 2029
Onshore wind project AF2-003, Marshall County
Onshore wind
303 MWWithdrawn / abandoned Marshall, ILPJM Oct 2019target 2023
Onshore wind project R79, Livingston County
Onshore wind
300 MWWithdrawn / abandoned Livingston, ILPJM Jan 2007target 2012
Onshore wind project R78, Livingston County
Onshore wind
300 MWWithdrawn / abandoned Livingston, ILPJM Jan 2007target 2013
Onshore wind project W1-030, Ford County
Onshore wind
300 MWWithdrawn / abandoned Ford, ILPJM Feb 2010target 2014
Gas project O27, Livingston County
Gas
300 MWWithdrawn / abandoned Livingston, ILPJM May 2005target 2015
Onshore wind project W1-031, Ford County
Onshore wind
300 MWWithdrawn / abandoned Ford, ILPJM Feb 2010target 2014
Onshore wind project J1757, Coles County
Onshore wind
300 MWWithdrawn / abandoned Coles, ILMISO Jun 2020target 2023
Onshore wind project AD2-142, Will County
Onshore wind
300 MWWithdrawn / abandoned Will, ILPJM Mar 2018target 2020
Battery storage project AI1-206
Battery storage
300 MWWithdrawn / abandoned ILPJM Sep 2022target 2029
Battery storage project J2497, Jefferson County
Battery storage
300 MWWithdrawn / abandoned Jefferson, ILMISO Sep 2022target 2026
Bright Stalk WF
Onshore wind
300 MWWithdrawn / abandoned Livingston, ILPJM May 2005target 2013
Battery storage project J2790, Christian County
Battery storage
300 MWWithdrawn / abandoned Christian, ILMISO Sep 2022target 2026
Onshore wind project G649, Edgar County
Onshore wind
300 MWWithdrawn / abandoned Edgar, ILMISO Jun 2006target 2008
Solar project J2626, Perry County
Solar
300 MWWithdrawn / abandoned Perry, ILMISO Sep 2022target 2026
Onshore wind project J101, Henry County
Onshore wind
300 MWWithdrawn / abandoned Henry, ILMISO Dec 2009target 2011
Solar project AD1-133, Grundy County
Solar
300 MWWithdrawn / abandoned Grundy, ILPJM Sep 2017target 2019
Onshore wind project AG1-399, Mclean County
Onshore wind · Wapella Bluffs Wind Project, LLC
300 MWWithdrawn / abandoned Mclean, ILPJM Sep 2020target 2024
Solar project J3269, Hamilton County
Solar
300 MWWithdrawn / abandoned Hamilton, ILMISO Apr 2024target 2027
Top Crop Wind Farm
Onshore wind
300 MWWithdrawn / abandoned Livingston, ILPJM May 2005target 2013
Solar project J3562, Vermilion County
Solar
300 MWWithdrawn / abandoned Vermilion, ILMISO Apr 2024target 2028
Onshore wind project J1676, Mclean County
Onshore wind
300 MWWithdrawn / abandoned Mclean, ILMISO Jun 2020target 2023
Battery storage project J2504, Coles County
Battery storage
300 MWWithdrawn / abandoned Coles, ILMISO Sep 2022target 2026
Onshore wind project J1702, Shelby County
Onshore wind
300 MWWithdrawn / abandoned Shelby, ILMISO Jun 2020target 2023
Onshore wind project J3700, Champaign County
Onshore wind
300 MWWithdrawn / abandoned Champaign, ILMISO Apr 2024target 2028
Battery storage project J2724, Shelby County
Battery storage
300 MWWithdrawn / abandoned Shelby, ILMISO Sep 2022target 2027
Solar project AH1-601, Lee County
Solar
300 MWWithdrawn / abandoned Lee, ILPJM Sep 2021target 2025
Onshore wind project G925, Dewitt County
Onshore wind
300 MWWithdrawn / abandoned Dewitt, ILMISO May 2010target 2010
Battery storage project AI1-205
Battery storage
300 MWWithdrawn / abandoned ILPJM Sep 2022target 2028
Onshore wind project J3995, Jasper County
Onshore wind
300 MWWithdrawn / abandoned Jasper, ILMISO Apr 2025target 2030
Solar project AG1-119, Dekalb County
Solar · Leeward Renewable Energy Development, LLC
300 MWWithdrawn / abandoned Dekalb, ILPJM Aug 2020target 2023
Onshore wind project AF1-318, Putnam County
Onshore wind · SkyYield Wind Farm, LLC
300 MWWithdrawn / abandoned Putnam, ILPJM Sep 2019target 2022
Onshore wind project J100, Henry County
Onshore wind
300 MWWithdrawn / abandoned Henry, ILMISO Dec 2009target 2012
Solar project J3878, Jefferson County
Solar
300 MWWithdrawn / abandoned Jefferson, ILMISO Dec 2024target 2029
Battery storage project AI1-204
Battery storage
300 MWWithdrawn / abandoned ILPJM Sep 2022target 2027
Solar project AF2-096, Will County
Solar · AEUG Will Solar, LLC
300 MWWithdrawn / abandoned Will, ILPJM Feb 2020target 2022
Southeast Chicago Energy Project (aka SCEP)
Gas
296 MWWithdrawn / abandoned Cook, ILPJM Sep 2020target 2024
Gas project J648, Cook County
Gas
296 MWWithdrawn / abandoned Cook, ILMISO Jun 2016
Onshore wind project AG2-197, Lee County
Onshore wind
296 MWWithdrawn / abandoned Lee, ILPJM Feb 2021target 2024
Onshore wind project AG1-121, Bureau County
Onshore wind · Leeward Renewable Energy Development, LLC
295 MWWithdrawn / abandoned Bureau, ILPJM Aug 2020target 2024
Page 2 of 14

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)